To maintain the Canadian National Master Specification's (NMS) relevance, the National Research Council of Canada (NRC) publishes a series of updates twice a year. The following summarizes the latest set of changes.
NMS summary of updates 2024-04
The 2024-04 NMS publication includes new and updated content related to energy efficiency, low embodied and operational carbon, smart building technologies, Canadian Forces Housing Agency (CFHA) guidelines, with additional options and requirements on material and design, advancing technology, current industry practices, and performance objectives.
New:
- Section 07 41 16 - Insulated Metal Roof Panels.
- Section 12 24 13 - Roller Window Shades.
- Section 25 35 13 - Integrated Automation Actuators and Operators.
- Section 26 09 13 - Electrical Power Monitoring.
Updates and targeted edits:
- Updates to reorganize content for clarity and in accordance with the SectionFormat™ standard.
- Updates to reference standards in accordance with the 2020 National Model Codes.
- Updates to 22 sections in Division 31 to include current industry practices and geotechnical requirements on-site during execution of work.
- Technical updates to 6 sections to include residential content and CFHA guidelines.
- Updates to 3 sections in Divisions 23 and 25 to include smart building technologies.
- Technical updates to 7 design specification Level 3 elements and 10 construction specification sections with requirements for low-carbon refrigerants and TBS' Standard on Embodied Carbon in Construction.
Editorial changes:
- Editorial changes and corrections to improve clarity of 44 sections.
Listing of NMS documents
Level 3 Element | Title | Status |
---|---|---|
1005 |
Table of Contents |
Updated |
A1010 |
Standard Foundations |
Targeted edits |
A4020 |
Structural Slabs-On-Grade |
Targeted edits |
C2030 |
Flooring |
Updated |
D2010 |
Domestic Water Distribution |
Targeted edits |
D3020 |
Heating Systems |
Targeted edits |
D3030 |
Cooling Systems |
Targeted edits |
D3050 |
Facility HVAC Distribution Systems |
Targeted edits |
Section | Title | Status |
---|---|---|
00 01 10 |
Table of Contents |
Updated |
00 01 15 |
List of Drawing Sheets |
Updated |
01 47 15 |
Sustainable Requirements: Construction |
Editorial changes |
01 50 13 |
Temporary Facilities and Controls for Dredging |
Editorial changes |
02 41 20 |
De-Commissioning and Removal of General Purpose (GP) Fume Hoods |
Editorial changes |
02 56 13 |
Waste Containment |
Editorial changes |
02 87 13.14 |
Precautions for Mould Remediation - Medium Precautions |
Editorial changes |
03 30 00 |
Cast-in-Place Concrete Formerly: Cast-In-Place Concrete |
Updated and renamed |
03 31 23.13 |
High-Performance Structural Concrete for Bridge Decks |
Updated |
03 45 00 |
Precast Architectural Concrete |
Editorial changes |
04 01 20.93 |
Testing and Sampling Brick Units for Restoration |
Editorial changes |
04 03 01.13 |
Period Masonry Cleaning |
Editorial changes |
04 03 05.16 |
Period Masonry Grouting |
Editorial changes |
04 03 05.21 |
Period Masonry Repointing |
Editorial changes |
04 03 21.19 |
Clay Brick Conservation Treatment |
Editorial changes |
05 50 00 |
Metal Fabrications |
Targeted edits |
06 03 01.31 |
Period Wood Storage and Protection |
Editorial changes |
06 03 05.74 |
Eradication of Insects in Period Wood |
Editorial changes |
06 03 50.13 |
Carvel Planking |
Editorial changes |
06 03 50.16 |
Steam Bending and Replacement of Curved Wood Members |
Editorial changes |
06 03 50.19 |
Caulking Period Vessels |
Editorial changes |
06 15 00 |
Wood Decking |
Updated |
06 41 93 |
Cabinet and Miscellaneous Hardware |
Editorial changes |
07 03 31.29 |
Conservation Treatment for Period Wood Shingles and Shakes |
Editorial changes |
07 27 00.01 |
Air Barriers - Descriptive or Proprietary |
Updated |
07 41 16 |
Insulated Metal Roof Panels |
New |
07 61 00 |
Sheet Metal Roofing |
Updated |
07 72 33 |
Roof Hatches |
Updated |
08 11 73 |
Sliding Metal Fire Doors |
Updated |
09 65 16 |
Resilient Sheet Flooring |
Updated |
09 65 19 |
Resilient Tile Flooring |
Updated |
09 96 53 |
Elastomeric Coatings |
Updated |
10 11 13 |
Chalkboards |
Updated |
10 22 33 |
Accordion Folding Partitions |
Editorial changes |
10 22 39 |
Folding Panel Partitions |
Editorial changes |
10 75 00 |
Flagpoles |
Updated |
11 11 00 |
Vehicle Service Equipment |
Editorial changes |
11 12 00 |
Parking Control Equipment |
Editorial changes |
11 13 19.13 |
Loading Dock Levellers Formerly: Loading Dock Levelers |
Updated and renamed |
11 13 19.23 |
Stationary Loading Dock Lifts Formerly: Loading Dock Lifts |
Updated and renamed |
11 40 00 Formerly: 11 40 10 |
Foodservice Equipment Formerly: Food Service Stock Equipment |
Targeted edits, renamed and renumbered |
11 81 19 |
Vacuum Cleaning Systems |
Editorial changes |
11 81 29 |
Facility Fall Protection |
Editorial changes |
11 82 19 |
Packaged Incinerators |
Editorial changes |
11 82 26 |
Facility Waste Compactors |
Editorial changes |
12 21 13 |
Horizontal Louvre Blinds |
Editorial changes |
12 21 16 |
Vertical Louvre Blinds |
Editorial changes |
12 24 13 |
Roller Window Shades |
New |
12 35 53.13 |
Metal Laboratory Casework |
Editorial changes |
21 08 00 |
Commissioning of Fire Suppression |
Editorial changes |
22 08 00 |
Commissioning of Plumbing |
Editorial changes |
23 05 05 |
Selective Demolition for Heating, Ventilating, and Air Conditioning (HVAC) |
Updated |
23 05 16 |
Expansion Fittings and Loops for HVAC Piping |
Editorial changes |
23 05 17 |
Pipe Welding |
Editorial changes |
23 05 23.01 |
Valves - Bronze |
Editorial changes |
23 05 23.02 |
Valves - Cast Iron |
Editorial changes |
23 05 23.03 |
Valves - Cast Steel |
Editorial changes |
23 05 23.04 |
Valves - Lubricated Plug |
Editorial changes |
23 05 23.05 |
Butterfly Valves |
Editorial changes |
23 05 29 |
Hangers and Supports for HVAC Piping and Equipment |
Editorial changes |
23 05 53 |
Identification for HVAC Piping and Equipment |
Editorial changes |
23 08 16 |
Cleaning and Start-Up of HVAC Piping Systems |
Editorial changes |
23 21 23 |
Hydronic Pumps |
Updated |
23 33 16 |
Dampers - Fire and Smoke |
Targeted edits |
25 05 53 Formerly: 25 05 54 |
Identification for Integrated Automation Formerly: EMCS: Identification |
Updated, renamed and renumbered |
25 35 13 |
Integrated Automation Actuators and Operators |
New |
25 90 00 Formerly: 25 90 01 |
Integrated Automation Control Sequences Formerly: EMCS: Site Requirements, Applications and Systems Sequences of Operation |
Updated, renamed and renumbered |
26 05 37 |
Wireways and Auxiliary Gutters |
Editorial changes |
26 05 38 |
Cellular Metal Floor Raceway Fittings |
Editorial changes |
26 05 39 |
Underfloor Raceways for Electrical Systems |
Editorial changes |
26 08 00 |
Commissioning of Electrical Systems Formerly: Commissioning of Electrical |
Editorial changes and renamed |
26 09 13 |
Electrical Power Monitoring |
New |
26 28 16.02 |
Moulded Case Circuit Breakers |
Targeted edits |
31 05 10 |
Corrected Maximum Dry Density for Fill |
Updated |
31 08 13 |
Pile Load Testing |
Updated |
31 14 13 |
Soil Stripping and Stockpiling |
Updated |
31 22 13 |
Rough Grading |
Updated |
31 22 16.13 |
Roadway Subgrade Reshaping |
Updated |
31 23 16.26 |
Rock Removal |
Updated |
31 24 13 |
Roadway Embankments |
Updated |
31 31 19.13 |
Chemical Vegetation Control |
Updated |
31 32 13.19 |
Lime Soil Stabilization |
Updated |
31 32 19.16 |
Geotextile Soil Stabilization |
Updated |
31 36 00 |
Gabions |
Updated |
31 36 19 |
Gabion Mattresses |
Updated |
31 37 00 |
Rip-Rap |
Updated |
31 53 13 |
Timber Cribwork |
Updated |
31 62 13.19 |
Precast Concrete Piles |
Updated |
31 62 16.16 |
Steel H Piles |
Updated |
31 62 19 |
Timber Piles |
Updated |
31 63 19 |
Bored and Socketed Piles |
Updated |
31 63 19.13 |
Rock Sockets for Piles |
Updated |
31 63 23 |
Bored Concrete Piles |
Updated |
31 63 24 |
Compacted Expanded-Base Concrete Piles |
Updated |
31 63 26.16 |
Concrete Caissons for Marine Construction |
Updated |
42 20 00 |
Process Cooling Equipment |
Targeted edits |
NMS summary of updates 2023-10
The 2023-10 NMS publication includes the following:
New:
- Section 00 31 00 - Available Project Information – identified as a key section for compiling existing project information.
- Section 02 26 00 - Hazardous Material Assessment – included to complement the existing suite of hazardous material sections.
- Section 06 83 16 - Fibreglass Reinforced Panelling – new section for a common interior finish.
- Section 10 74 46 - Window Wells – included to better capture Canadian Forces Housing Agency (CFHA) guidelines.
Updates and targeted edits:
- Updates to reorganize content for clarity and in accordance with the SectionFormat™ standard.
- Updates to reference standards in accordance with the 2020 National Model Codes.
- Updates to 6 sections in Divisions 10, 23, and 26 to include residential content and CFHA guidelines.
- Updates to include additional options and requirements on material and design, advancing technology, current industry practices, and performance objectives.
- Technical updates to 3 design specification Level 3 elements and 16 construction specification sections with low-carbon content and guidance.
Editorial changes:
- Editorial changes and corrections to improve clarity of 20 sections.
Deleted:
- One section was deleted (Section 01 14 25 - Designated Substances Report), with content transferred into new sections (Section 00 31 00 - Available Project Information and Section 02 26 00 - Hazardous Material Assessment).
Listing of NMS documents
Level 3 Element | Title | Status |
---|---|---|
1005 |
Table of Contents |
Updated |
A1020 |
Special Foundations |
Updated |
A2010 |
Walls for Subgrade Enclosures |
Updated |
A4010 |
Standard Slabs-On-Grade |
Updated |
Section | Title | Status |
---|---|---|
00 01 10 |
Table of Contents |
Updated |
00 11 19.53 |
Request for Proposal - Design Build (Single Prime Contract) |
Editorial changes |
00 31 00 |
Available Project Information |
New |
01 14 25 |
Designated Substances Report |
Deleted |
01 35 29.13 |
Health, Safety, and Emergency Response Procedures for Contaminated Sites |
Editorial changes |
01 35 43 |
Environmental Procedures |
Editorial changes |
01 71 00 |
Examination and Preparation |
Updated |
02 42 19.48 Formerly: 01 74 19.13 |
Carpeting Recycling Formerly: Carpet Reclamation |
Renumbered renamed and updated |
02 03 44 |
Shoring and Support of Period Structures |
Editorial changes |
02 26 00 |
Hazardous Material Assessment |
New |
02 41 19 Formerly: 02 41 00.08 |
Selective Demolition Formerly: Demolition - Minor Works |
Renumbered renamed and updated |
02 41 13.13 |
Paving Removal |
Updated |
02 41 16 |
Structure Demolition |
Editorial changes |
02 42 00 |
Removal and Salvage of Construction Materials |
Editorial changes |
02 42 13 |
Deconstruction of Structures |
Editorial changes |
02 83 10 |
Lead-Based Paint Abatement - Minimum Precautions Formerly: Lead-Base Paint Abatement - Minimum Precautions |
Renamed and updated |
02 83 11 |
Lead-Based Paint Abatement - Intermediate Precautions Formerly: Lead-Base Paint Abatement - Intermediate Precautions |
Renamed and updated |
02 83 12 |
Lead-Based Paint Abatement - Maximum Precautions Formerly: Lead-Base Paint Abatement - Maximum Precautions |
Renamed and updated |
03 10 00 |
Concrete Forming and Accessories |
Targeted edits |
04 05 00 |
Common Work Results for Masonry |
Updated |
06 03 05.75 |
Antiseptic Treatment of Period Wood |
Editorial changes |
06 03 13.23 |
Conservation Treatment of Period Heavy Timber |
Editorial changes |
06 17 00 |
Shop-Fabricated Structural Wood |
Editorial changes |
06 17 53 |
Shop-Fabricated Wood Trusses |
Editorial changes |
06 18 00 |
Glued-Laminated Construction |
Editorial changes |
06 40 23.13 |
Plastic Laminate Finishing for Interior Architectural Woodwork |
Editorial changes |
06 83 16 |
Fibreglass Reinforced Panelling |
New |
07 03 31.26 |
Conservation Treatment for Period Slate Shingles |
Editorial changes |
07 03 32.16 |
Conservation Treatment for Period Concrete Roof Tiles |
Editorial changes |
07 24 23 |
Direct-Applied Finish Systems |
Editorial changes |
07 71 29 |
Manufactured Roof Expansion Joints |
Updated |
08 36 13.19 |
Sectional Plastic Doors |
Editorial changes |
08 36 19.16 |
Multi-Leaf Vertical Lift Metal Doors |
Editorial changes |
08 87 23.16 |
Security Films |
Editorial changes |
09 01 90.63 |
Interior Repainting |
Updated |
09 64 23 |
Wood Parquet Flooring |
Editorial changes |
09 68 13 |
Tile Carpeting |
Updated |
10 74 46 |
Window Wells |
New |
11 13 13 |
Loading Dock Bumpers |
Updated |
11 13 16 |
Loading Dock Seals and Shelters |
Updated |
11 41 20 Formerly: 11 41 23 |
Walk-in Coolers and Freezers Formerly: Walk-In Coolers and Freezers |
Renumbered renamed and updated |
22 15 00 |
General Service Compressed-Air Systems Formerly: General Service Compressed - Air Systems |
Targeted edits |
23 34 00.13 |
Domestic Fans |
Updated |
23 52 00 |
Heating Boilers |
Updated |
23 64 16 |
Centrifugal Water Chillers |
Targeted edits |
23 64 19 |
Reciprocating Water Chillers |
Targeted edits |
23 64 26 |
Rotary-Screw Water Chillers |
Targeted edits |
23 65 10 |
Condensers, Coolers, and Cooling Towers |
Targeted edits |
23 73 00.13 |
Air Handling - Built-Up |
Targeted edits |
23 73 00.16 |
Air Handling Units - Packaged |
Targeted edits |
23 74 00 |
Packaged Outdoor HVAC Equipment |
Targeted edits |
23 81 23 |
Computer Room Air Conditioning |
Targeted edits |
23 81 40 |
Air and Water Source Unitary Heat Pumps |
Targeted edits |
23 81 46 |
Water Source Unitary Heat Pumps |
Targeted edits |
23 82 23 |
Unit Ventilators |
Targeted edits |
23 82 36 |
Finned Tube Radiation Heaters |
Targeted edits |
26 24 16.01 |
Panelboards Breaker Type |
Targeted edits |
26 27 73 |
Door Chimes |
Targeted edits |
26 29 03 |
Control Devices |
Targeted edits |
26 29 33 |
Controllers for Fire Pump Drivers |
Targeted edits |
26 33 43 |
Battery Chargers |
Targeted edits |
31 05 16 |
Aggregates for Earthwork |
Updated |
31 32 33 |
Shotcrete Soil Slope Stabilization |
Updated |
31 33 13.13 |
Rock Scaling |
Updated |
31 33 13.16 |
Rock Anchors |
Updated |
31 61 13 |
General Requirements for Pile Foundations |
Updated |
31 62 16.14 |
Steel Sheet Pile Cells |
Updated |
31 62 16.19 |
Tubular Steel Piles Formerly: Unfilled Tubular Steel Piles |
Renamed and updated |
NMS summary of updates 2023-04
The 2023-04 NMS publication includes the following:
- Updates to reorganize content in accordance with SectionFormat™ and for clarity.
- Updates to reference standards in accordance with the 2020 National Model Codes.
- Updates to include additional options and requirements on material and design, advancing technology, current industry practices, and performance objectives.
- Updates to include bird-friendly design requirements in Level 3 Element B2020.
- 7 new sections in Divisions 22, 23 and 31 that also include content on low-carbon and climate resilient construction.
- 4 deleted sections in Divisions 01, 23 and 31 with relevant content redistributed to other updated sections.
Technical updates
Design Specifications
Section | Title | Status |
---|---|---|
1005
Formerly: 1010 |
Table of Contents | Renumbered and updated |
A1010 | Standard Foundations | Updated |
A1020 | Special Foundations | Updated |
A2010 | Walls for Subgrade Enclosures
Formerly: Walls-for-Subgrade Enclosure |
Renamed and updated |
A4010 | Standard Slabs-On-Grade | Updated |
A4020 | Structural Slabs-On-Grade | Updated |
A6010 | Building Subdrainage | Updated |
B2020 | Exterior Windows | Updated |
Construction Specifications
Section | Title | Status |
---|---|---|
00 01 10 | Table Of Contents | Updated |
01 35 43.10 | Environmental Procedures - Bridges | Updated |
01 47 13 | Sustainable Requirements: Concept Design | Deleted |
01 47 19 | Sustainable Requirements: Operation | Deleted |
04 03 05.13 | Period Masonry Mortaring | Updated |
05 12 33 | Structural Steel for Bridges | Updated |
08 36 13.13 | Sectional Wood Doors | Updated |
09 23 00 | Gypsum Plastering | Updated |
09 58 00 | Integrated Ceiling Assemblies | Updated |
09 63 40 | Stone Flooring | Updated |
09 64 53 | Resilient Wood Flooring Assemblies | Updated |
09 66 16 | Terrazzo Floor Tile | Updated |
09 66 23 | Resinous Matrix Terrazzo Flooring | Updated |
09 69 00 | Access Flooring | Updated |
10 44 00 | Fire Protection Specialties | Updated |
21 13 13 | Wet Pipe Sprinkler Systems | Editorial changes |
22 07 19 | Plumbing Piping Insulation | New |
22 11 16 | Domestic Water Piping | Editorial changes |
23 05 48.16 | Seismic Restraint Systems (SRS) - Type P2 Buildings | Deleted |
23 07 19 | HVAC Piping Insulation | Updated |
23 08 13 | Performance Verification HVAC Systems | Updated |
23 21 13.33 | Ground-Loop Heat-Pump Piping | New |
23 37 20 | Louvres, Intakes and Vents | Updated |
23 57 00 | Heat Exchangers for HVAC | Updated |
23 64 16 | Centrifugal Water Chillers | Updated |
23 64 19 | Reciprocating Water Chillers | Updated |
23 64 26 | Rotary-Screw Water Chillers | Updated |
23 65 16 | Natural Draft Cooling Towers | Updated |
23 73 00.13 | Air Handling - Built-Up | Updated |
23 73 00.16 | Air Handling Units - Packaged | Updated |
23 74 00 | Packaged Outdoor HVAC Equipment | Updated |
23 81 23 | Computer Room Air Conditioning | Updated |
23 81 43 | Air Source Unitary Heat Pumps | New |
31 09 16.01 | Pile Driving Templates | Deleted |
31 32 33 | Shotcrete Soil Slope Stabilization | New |
31 33 13.13 | Rock Scaling | New |
31 33 13.16 | Rock Anchors | New |
31 33 13.19 | Rock Slope Barriers | New |
31 61 13 | General Requirements for Pile Foundations
Formerly: Pile Foundations, General Requirements |
Renamed and updated |
31 62 16.13 | Sheet Steel Piles | Updated |
31 62 16.14 | Steel Sheet Pile Cells | Updated |
32 31 13 | Chain-Link Fences and Gates
Formerly: Chain Link Fences and Gates |
Renamed and updated |
33 56 13 | Aboveground Fuel - Storage Tanks | Updated |
NMS summary of updates 2022-10
The 2022-10 NMS publication includes the following:
- The development of new sections in Division 31-Earthworks and Division 32-Exterior Improvements, that cover the requirements for shotcrete and soil slope and rock stabilization;
- New Section 11 11 36.10 - Electric Vehicle Charging Units, which covers the requirements for electric vehicle charging stations;
- Technical updates to over 60 design and construction specification sections with a focus on mechanical systems and other requirements for net-zero carbon building operation and climate resiliency; and
- Updating the reference standards of the included sections to the 2020 National Model Codes.
Technical updates
Design Specifications
Section | Title | Status |
---|---|---|
1010 | Table of Contents | Updated |
E1010 | Vehicle and Pedestrian Equipment | Updated |
Construction Specifications
Section | Title | Status |
---|---|---|
00 01 10 | Table of Contents | Updated |
01 41 00 | Regulatory Requirements | Updated |
01 51 00 | Temporary Utilities | Updated |
01 91 13 | General Commissioning Requirements | Updated |
02 50 00 | Site Remediation | Editorial changes |
03 01 37 | Concrete Restoration | Updated |
03 10 00 | Concrete Forming and Accessories | Updated |
03 11 19 | Insulating Concrete Forming | Updated |
03 20 00 | Concrete Reinforcing | Editorial changes |
03 30 00 | Cast-In-Place Concrete | Editorial changes |
03 30 00.09 | Cast-In-Place Concrete - Short Form | Updated |
03 35 00 | Concrete Finishing | Updated |
03 35 46 | Concrete Topical Treatments
Formerly: Concrete Floor Hardening |
Renamed and updated |
03 37 13 | Shotcrete | Updated |
03 37 26 | Underwater Placed Concrete | Updated |
03 41 00 | Precast Structural Concrete | Updated |
03 41 36 | Precast Structural Post-Tensioned Concrete | Updated |
03 45 00 | Precast Architectural Concrete | Editorial changes |
03 48 00 | Precast Concrete Specialties | Updated |
04 20 00.08 | Masonry for Minor Works | Updated |
05 41 00 | Structural Metal Stud Framing | Updated |
06 14 00 | Treated Wood Foundations | Updated |
07 81 00 | Applied Fire Protection
Formerly: Applied Fireproofing |
Renamed and updated |
08 11 13
Formerly: 08 11 00 |
Hollow Metal Doors and Frames
Formerly: Metal Doors and Frames |
Renumbered, renamed and updated |
08 14 73 | Sliding Wood and Plastic Doors | Updated |
08 42 26.33 | Swinging All Glass Entrances | Updated |
08 42 29 | Automatic Entrances | Updated |
08 62 00 | Unit Skylights | Updated |
08 71 00 | Door Hardware | Updated |
09 03 25 | Conservation Treatment for Period Plastering | Updated |
09 30 15 | Quarry and Paver Tiling | Updated |
09 51 13 | Acoustical Panel Ceilings | Updated |
09 54 23 | Linear Metal Ceilings | Updated |
09 72 16 | Vinyl-Coated Fabric Wall Coverings | Updated |
09 84 00
Formerly: 09 80 00 |
Acoustic Room Components
Formerly: Acoustic treatment |
Renumbered, renamed and updated |
11 11 36.10 | Electric Vehicle Charging Units | New |
13 34 19 | Metal Building Systems | Editorial changes |
21 12 00 | Fire-Suppression Standpipes
Formerly: Fire-Suppression Standpipes and Hose Assemblies |
Renamed and updated |
21 13 13 | Wet Pipe Sprinkler Systems | Updated |
21 13 16 | Dry Pipe Sprinkler Systems | Updated |
23 05 13 | Common Motor Requirements for HVAC Equipment | Updated |
23 05 19 | Meters and Gauges for HVAC Piping | Updated |
23 05 19.13 | Thermometers and Pressure Gauges - Piping Systems | Updated |
23 05 33 | Heat Tracing for HVAC Piping | Updated |
23 05 93 | Testing, Adjusting and Balancing for HVAC | Updated |
23 05 93.13 | Testing, Adjusting and Balancing of Fume Hoods | Updated |
23 05 94 | Pressure Testing of Ducted Air Systems | Updated |
23 07 13 | Duct Insulation | Updated |
23 07 16 | HVAC Equipment Insulation | Updated |
23 07 19 | HVAC Piping Insulation | Updated |
23 08 00 | Commissioning of HVAC | Editorial changes |
23 21 23 | Hydronic Pumps | Updated |
23 33 16 | Dampers - Fire and Smoke | Updated |
23 33 46 | Flexible Ducts | Updated |
23 51 00 | Breechings, Chimneys and Stacks | Updated |
23 54 16 | Fuel-Fired Furnaces | Updated |
23 64 13 | Absorption Water Chillers | Updated |
23 81 46 | Water Source Unitary Heat Pumps | New |
26 29 33
Formerly: 26 29 02 |
Controllers for Fire Pump Drivers
Formerly: Fire Pump Control |
Renumbered, renamed and updated |
31 32 36 | Soil Nailing | New |
31 33 23 | Rock Slope Drape Mesh | New |
31 33 26 | Rock Slope Pinned Mesh | New |
31 33 29 | Rock Slope Drains | New |
32 32 34 | Reinforced Soil Retaining Walls | Updated |
NMS summary of updates 2022-04
The 2022-04 NMS publication includes: technical updates to over 300 design and construction specification Sections with content and guidance for net-zero carbon building operation and climate resiliency.
Technical updates
Design Specifications
Section | Title | Status |
---|---|---|
1020 | Project Brief | Editorial changes |
1030 | Project Criteria | Editorial changes |
A1010 | Standard Foundations | Editorial changes |
A1020 | Special Foundations | Editorial changes |
A2010 | Walls for Subgrade Enclosures | Editorial changes |
A4010 | Standard Slabs-On-Grade | Editorial changes |
A4020 | Structural Slabs-On-Grade | Editorial changes |
B1010 | Floor Construction | Editorial changes |
B1020 | Roof Construction | Editorial changes |
B2010 | Exterior Walls | Editorial changes |
B2020 | Exterior Windows | Editorial changes |
B2050 | Exterior Doors and Grilles | Editorial changes |
B2080 | Exterior Wall Appurtenances | Editorial changes |
B3010 | Roofing | Editorial changes |
B3020 | Roof Appurtenances | Editorial changes |
B3040 | Traffic Bearing Horizontal Enclosures | Editorial changes |
B3060 | Horizontal Openings | Editorial changes |
B3080 | Overhead Exterior Enclosures | Editorial changes |
C1070 | Suspended Ceiling Construction | Editorial changes |
C2010 | Wall Finishes | Editorial changes |
C2050 | Ceiling Finishes | Editorial changes |
D1010 | Vertical Conveying Systems | Editorial changes |
D2010 | Domestic Water Distribution | Editorial changes |
D2020 | Sanitary Drainage | Editorial changes |
D2030 | Building Support Plumbing Systems | Editorial changes |
D2050 | General Service Compressed-Air | Editorial changes |
D3010 | Facility Fuel Systems | Editorial changes |
D3020 | Heating Systems | Editorial changes |
D3030 | Cooling Systems | Editorial changes |
D3050 | Facility HVAC Distribution Systems | Editorial changes |
D3060 | Ventilation | Editorial changes |
D5020 | Electrical Service and Distribution | Editorial changes |
D5030 | General Purpose Electrical Power | Editorial changes |
D5040 | Lighting | Editorial changes |
D5080 | Miscellaneous Electrical Systems | Editorial changes |
D6010 | Data Communications | Editorial changes |
D6060 | Distributed Communications and Monitoring | Editorial changes |
D7010 | Access Control and Intrusion Detection | Editorial changes |
D7030 | Electronic Surveillance | Editorial changes |
D7050 | Detection and Alarm | Editorial changes |
D8010 | Integrated Automation Facility Controls | Editorial changes |
E1010 | Vehicle and Pedestrian Equipment | Editorial changes |
E1030 | Commercial Equipment | Editorial changes |
E1040 | Institutional Equipment | Editorial changes |
E1060 | Residential Equipment | Editorial changes |
E1070 | Entertainment and Recreational Equipment | Editorial changes |
E1090 | Other Equipment | Editorial changes |
G3050 | Site Energy Distribution | Editorial changes |
G4010 | Site Electrical Distribution Systems | Editorial changes |
G4050 | Site Lighting | Editorial changes |
G5010 | Site Communications Systems | Editorial changes |
Z1040 | Quality Requirements | Editorial changes |
Construction Specifications
Section | Title | Status |
---|---|---|
00 01 10 | Table of Contents | Updated |
01 33 29 | Sustainable Design Reporting | Editorial changes |
01 35 21 | LEED Requirements | Editorial changes |
01 35 35 | DND Fire Safety Requirements | Updated |
01 47 13 | Sustainable Requirements: Concept Design | Updated |
01 47 15 | Sustainable Requirements: Construction | Updated |
01 47 19 | Sustainable Requirements: Operation | Updated |
01 71 00 | Examination and Preparation | Updated |
02 22 10 | Existing Building Condition Assessments | Editorial changes |
02 25 29.23 | Roofing Investigations - Thermographic | Editorial changes |
02 27 13 | Thermographic Assessment - Building Envelope | Editorial changes |
03 11 19 | Insulating Concrete Forming
Formerly: Insulating Concrete forms |
Renamed and updated |
03 20 00 | Concrete Reinforcing | Editorial changes |
03 30 00 | Cast-In-Place Concrete | Editorial changes |
03 30 00.09 | Cast-In-Place Concrete - Short form | Editorial changes |
03 37 26 | Underwater Placed Concrete | Editorial changes |
03 41 00 | Precast Structural Concrete | Editorial changes |
03 41 36 | Precast Structural Post-Tensioned Concrete | Editorial changes |
03 45 00 | Precast Architectural Concrete | Editorial changes |
03 48 00 | Precast Concrete Specialties | Editorial changes |
04 05 19 | Masonry Anchorage and Reinforcing | Updated |
04 05 23 | Masonry Accessories | Updated |
04 20 00.08 | Masonry for Minor Works | Updated |
04 21 13 | Brick Masonry | Updated |
04 21 19 | Clay Tile Masonry | Updated |
04 22 00 | Concrete Unit Masonry | Updated |
04 23 00 | Glass Unit Masonry | Updated |
04 43 13 | Marble Veneer Cladding | Updated |
04 43 16 | Granite Veneer Cladding | Updated |
04 43 19 | Collected Stone Veneer Cladding | Updated |
04 43 23 | Quarried Stone Veneer Cladding | Updated |
04 43 26 | Dimension Stone Veneer Cladding | Editorial changes |
04 71 13 | Calcium Silicate Manufactured Brick Masonry | Updated |
04 71 13.13 | Prefaced Calcium Silicate Manufactured Brick Masonry | Updated |
04 73 13 | Calcium Silicate Manufactured Stone Masonry | Updated |
05 12 23 | Structural Steel for Buildings | Updated |
05 14 00 | Structural Aluminum Framing
Formerly: Structural Aluminum for Buildings |
Renamed and updated |
05 21 00 | Steel Joist Framing | Updated |
05 31 00 | Steel Decking | Updated |
05 41 00 | Structural Metal Stud Framing | Updated |
06 17 00 | Shop-Fabricated Structural Wood | Editorial changes |
07 03 30.16 | Conservation Treatment for Period Board Roofing | Updated |
07 03 31.26 | Conservation Treatment for Period Slate Shingles | Updated |
07 03 32.16 | Conservation Treatment for Period Concrete Roof Tiles | Updated |
07 03 33.13 | Conservation Treatment for Period Sod Roofing | Updated |
07 03 41.13 | Conservation Treatment for Period Metal Roof Panels | Updated |
07 08 13 | Building Enclosure Performance Testing | Updated |
07 11 13 | Bituminous Dampproofing | Updated |
07 12 13 | Built-Up Asphalt Waterproofing | Updated |
07 13 52 | Modified Bituminous Sheet Waterproofing | Updated |
07 13 53 | Elastomeric Sheet Waterproofing | Updated |
07 14 13 | Hot Fluid-Applied Rubberized Asphalt Waterproofing | Updated |
07 16 19 | Metal Oxide Waterproofing | Updated |
07 17 13 | Bentonite Panel Waterproofing | Updated |
07 21 13 | Board Insulation | Updated |
07 21 16 | Blanket Insulation | Updated |
07 21 23 | Loose-Fill Insulation | Updated |
07 21 26.13 | Blown Insulation - Cellulose | Updated |
07 21 29 | Sprayed Insulation
Formerly: Sprayed Insulation - Polyurethane Foam |
Renamed and updated |
07 24 10.01 | Exterior Insulation and Finish Systems - Panelized | Updated |
07 24 23
Formerly: 07 24 10.03 |
Direct-Applied Finish Systems
Formerly: Exterior Finish - Direct Applied |
Renumbered, renamed and updated |
07 26 00 | Vapour Retarders | Updated |
07 27 00.01 | Air Barriers - Descriptive Or Proprietary | Updated |
07 27 00.02 | Air Barriers - Performance | Updated |
07 42 13.13
Formerly: 07 42 13.23 |
Formed Metal Wall Panels
Formerly: Metal Composite Material Wall Panels |
Renumbered, renamed and updated |
07 42 43 | Composite Wall Panels | Updated |
07 42 46 | Cementitious Wall Panels
Formerly: Fibre Reinforced Cementitious Wall Panels |
Renamed and updated |
07 46 19 | Steel Siding | Updated |
07 46 23 | Wood Siding | Updated |
07 51 00 | Built-Up Bituminous Roofing | Updated |
07 52 00 | Modified Bituminous Membrane Roofing | Updated |
07 53 23 | Ethylene Propylene Diene Monomer Roofing | Updated |
07 55 63 | Vegetated Protected Membrane Roofing | Updated |
07 56 13 | Hot Fluid-Applied Rubberized Asphalt Roofing | Updated |
07 61 00 | Sheet Metal Roofing | Updated |
07 62 00 | Sheet Metal Flashing and Trim | Updated |
07 71 29 | Manufactured Roof Expansion Joints | Updated |
07 72 33 | Roof Hatches | Updated |
07 84 00 | Firestopping
Formerly: Fire Stopping and Smoke Seals |
Renamed and updated |
07 92 00 | Joint Sealants | Updated |
07 95 13 | Expansion Joint Cover Assemblies | Updated |
08 03 11 | Historic - Period Wood Doors | Updated |
08 03 14.33 | Conservation Treatment for Period Stile and Rail Wood Doors | Updated |
08 03 51.23 | Conservation Treatment for Period Steel Windows | Updated |
08 03 52 | Conservation Treatment for Period Wood Windows | Updated |
08 10 69
Formerly: 08 11 69 |
Storm Doors and Frames
Formerly: Metal Storm Doors and Frames |
Renumbered, renamed and updated |
08 11 00 | Metal Doors and Frames | Editorial changes |
08 11 16 | Aluminum Doors and Frames | Updated |
08 11 19 | Stainless-Steel Doors and Frames | Updated |
08 11 73
Formerly: 08 13 73 |
Sliding Metal Fire Doors
Formerly: Sliding Metal Doors |
Renumbered, renamed and updated |
08 14 00
Formerly: 08 14 16 |
Wood Doors
Formerly: Flush Wood Doors |
Renumbered, renamed and updated |
08 14 73 | Sliding Wood and Plastic Doors | Editorial changes |
08 31 00 | Access Doors and Panels | Updated |
08 33 00 | Overhead Coiling Doors and Grilles | Updated |
08 36 13.16 | Sectional Metal Doors | Updated |
08 36 13.19 | Sectional Plastic Doors | Updated |
08 36 19 | Multi-Leaf Vertical Lift Doors | Updated |
08 36 19.13 | Multi-Leaf Vertical Lift Wood Doors | Updated |
08 36 19.16 | Multi-Leaf Vertical Lift Metal Doors | Updated |
08 38 16 | Flexible Traffic Doors | Updated |
08 42 26.33 | Swinging All Glass Entrances | Updated |
08 42 29 | Automatic Entrances | Updated |
08 44 13 | Glazed Aluminum Curtain Walls | Updated |
08 44 23 | Structural Sealant Glazed Curtain Walls | Updated |
08 50 00 | Windows | Updated |
08 62 00 | Unit Skylights | Updated |
08 71 00 | Door Hardware | Updated |
08 80 00 | Glazing | Updated |
08 87 23.16 | Security Films | Updated |
08 90 00 | Louvres and Vents | Updated |
09 30 13 | Ceramic Tiling | Updated |
09 54 23 | Linear Metal Ceilings | Editorial changes |
09 58 00 | Integrated Ceiling Assemblies | Editorial changes |
09 64 23 | Wood Parquet Flooring | Updated |
09 64 29 | Wood Strip and Plank Flooring | Updated |
09 65 16 | Resilient Sheet Flooring | Updated |
14 12 00 | Electric Dumbwaiters | Updated |
14 20 03 | Freight Elevators | Updated |
14 20 06 | Passenger Elevators | Updated |
14 31 00 | Escalators | Updated |
14 32 00 | Moving Walks | Updated |
14 42 00 | Wheelchair Lifts | Updated |
14 43 19 | Suspended Powered Platforms | Editorial changes |
14 43 21 | Platform Lifts - Hydraulic | Editorial changes |
22 10 10 | Plumbing Pumps | Editorial changes |
22 11 16 | Domestic Water Piping | Editorial changes |
22 15 00 | General Service Compressed - Air Systems | Editorial changes |
22 33 00 | Electrical Domestic Water Heaters | Editorial changes |
22 42 13 | Commercial Water Closets, Urinals, and Bidets | Editorial changes |
22 42 16 | Commercial Lavatories and Sinks | Editorial changes |
22 42 19 | Commercial Bathtubs and Showers | Editorial changes |
22 47 00 | Drinking Fountains and Water Coolers | Editorial changes |
23 05 00 | Common Work Results for HVAC | Editorial changes |
23 05 05 | Selective Demolition for Heating, Ventilating, and Air Conditioning (HVAC) | Editorial changes |
23 05 13 | Common Motor Requirements for HVAC Equipment | Editorial changes |
23 05 15 | Common Installation Requirements for HVAC Pipework | Editorial changes |
23 05 19 | Meters and Gauges for HVAC Piping | Editorial changes |
23 05 19.13 | Thermometers and Pressure Gauges - Piping Systems | Editorial changes |
23 05 33 | Heat Tracing for HVAC Piping | Editorial changes |
23 05 93 | Testing, Adjusting and Balancing for HVAC | Editorial changes |
23 05 93.13 | Testing, Adjusting and Balancing of Fume Hoods | Editorial changes |
23 05 94 | Pressure Testing of Ducted Air Systems | Editorial changes |
23 07 13 | Duct Insulation | Editorial changes |
23 07 16 | HVAC Equipment Insulation | Editorial changes |
23 07 19 | HVAC Piping Insulation | Editorial changes |
23 08 00 | Commissioning of HVAC | Editorial changes |
23 08 13 | Performance Verification HVAC Systems | Editorial changes |
23 08 16 | Cleaning and Start-Up of HVAC Piping Systems | Editorial changes |
23 09 33 | Electric and Electronic Control System for HVAC | Editorial changes |
23 09 43 | Pneumatic Control System for HVAC | Editorial changes |
23 11 13 | Facility Fuel Oil Piping | Editorial changes |
23 11 23 | Facility Natural Gas Piping | Editorial changes |
23 11 26 | Facility Liquid-Petroleum Gas Piping | Editorial changes |
23 21 13.01 | Hydronic Systems: Copper | Editorial changes |
23 21 13.02 | Hydronic Systems: Steel | Editorial changes |
23 21 13.03 | Press Joint Piping Systems Hydronic Systems | Editorial changes |
23 21 16 | Hydronic Piping Specialties | Editorial changes |
23 21 23 | Hydronic Pumps | Editorial changes |
23 22 13 | Steam and Condensate Heating Piping | Editorial changes |
23 22 13.13 | High Pressure Steam and Condensate Heating Piping Systems | Editorial changes |
23 22 16 | Steam Specialties | Editorial changes |
23 22 23 | Steam Condensate Pumps | Editorial changes |
23 23 00 | Refrigerant Piping | Editorial changes |
23 33 53 | Duct Liners | Editorial changes |
23 34 00 | HVAC Fans | Editorial changes |
23 34 00.13 | Domestic Fans | Editorial changes |
23 34 23.13 | Packaged Roof and Wall Exhausters | Editorial changes |
23 35 16 | Engine Exhaust Systems | Editorial changes |
23 36 00 | Air Terminal Units | Editorial changes |
23 37 13 | Diffusers, Registers and Grilles | Editorial changes |
23 37 20 | Louvres, Intakes and Vents | Editorial changes |
23 38 13 | Commercial Kitchen Hoods | Editorial changes |
23 38 17 | Perchloric Acid Fume Hood and Exhaust System - Stainless Steel | Editorial changes |
23 38 18 | Perchloric Acid Fume Hood and Exhaust System - Plastic | Editorial changes |
23 52 00 | Heating Boilers | Editorial changes |
23 54 13 | Electric-Resistance Furnaces | Editorial changes |
23 54 16 | Fuel-Fired Furnaces | Editorial changes |
23 56 13.13 | Heating Solar Flat- Plate Collectors | Editorial changes |
23 57 00 | Heat Exchangers for HVAC | Editorial changes |
23 64 13 | Absorption Water Chillers | Editorial changes |
23 64 16 | Centrifugal Water Chillers | Editorial changes |
23 64 19 | Reciprocating Water Chillers | Editorial changes |
23 64 26 | Rotary-Screw Water Chillers | Editorial changes |
23 65 10 | Condensers, Coolers and Cooling Towers | Editorial changes |
23 65 16 | Natural Draft Cooling Towers | Editorial changes |
23 72 00 | Air-To-Air Energy Recovery Equipment | Editorial changes |
23 73 00.13 | Air Handling - Built-Up | Editorial changes |
23 73 00.16 | Air Handling Units - Packaged | Editorial changes |
23 74 00 | Packaged Outdoor HVAC Equipment | Editorial changes |
23 81 23 | Computer Room Air Conditioning | Editorial changes |
23 81 40 | Air and Water Source Unitary Heat Pumps | Editorial changes |
23 82 00.13 | forced Air Heaters | Editorial changes |
23 82 00.16 | Incremental Heating and Cooling Units | Editorial changes |
23 82 16.14 | Electric-Resistance Air Coils | Editorial changes |
23 82 19 | Fan Coil Units | Editorial changes |
23 82 23 | Unit Ventilators | Editorial changes |
23 82 33.13 | Residential Convectors | Editorial changes |
23 82 33.16 | Commercial Convectors | Editorial changes |
23 82 33.19 | Cabinet Convector Heaters | Editorial changes |
23 82 36 | Finned Tube Radiation Heaters | Editorial changes |
23 82 39 | Unit Heaters | Editorial changes |
23 82 39.26 | Liquid Heaters | Editorial changes |
23 83 00 | Radiant Heating Units | Editorial changes |
23 83 00.13 | Radiant Heaters - Electric Infrared | Editorial changes |
23 83 13 | Radiant Heating Electric Cables | Editorial changes |
23 83 13.19 | Radiant Heating Electric Cables - Snow Melting | Editorial changes |
23 83 13.23 | Radiant Heating Electric Cables - Floor Warming | Editorial changes |
23 84 13 | Humidifiers | Editorial changes |
25 01 11 | EMCS: Start-Up, Verification and Commissioning | Editorial changes |
25 01 12 | EMCS: Training | Editorial changes |
25 05 01 | EMCS: General Requirements | Editorial changes |
25 05 02 | EMCS: Submittals and Review Process | Editorial changes |
25 05 03 | EMCS: Project Record Documents | Editorial changes |
25 05 54 | EMCS: Identification | Editorial changes |
25 05 60 | EMCS: Field Installation | Editorial changes |
25 08 20 | EMCS: Warranty and Maintenance | Editorial changes |
25 10 01 | EMCS: Local Area Network (LAN) | Editorial changes |
25 10 02 | EMCS: Operator Work Station (OWS) | Editorial changes |
25 30 01 | EMCS: Building Controllers | Editorial changes |
25 30 02 | EMCS: Field Control Devices | Editorial changes |
25 90 01 | EMCS: Site Requirements, Applications and Systems Sequences of Operation | Editorial changes |
26 05 80 | Fractional Horsepower Motors | Editorial changes |
26 05 81 | Motors: 0.746 to 149 kW | Editorial changes |
26 06 31 | Diesel Electric Generating Units Appendix A - Technical Data form | Editorial changes |
26 08 00 | Commissioning of Electrical | Editorial changes |
26 09 23.01 | Metering and Switchboard Instruments | Editorial changes |
26 09 23.02 | Lighting Control Devices - Photoelectric | Editorial changes |
26 09 23.03 | Lighting Control Devices - Incandescent Dimming | Editorial changes |
26 09 24 | Lighting Control Devices - Low Voltage | Editorial changes |
26 09 43 | Network Lighting Controls | Editorial changes |
26 11 00.01 | Outdoor Substation to 15 kV | Editorial changes |
26 11 13.01 | Unit Substation to 15 kV | Editorial changes |
26 18 39.01 | Motor Controllers - 2000 to 5000 V (Non-Hazardous) | Editorial changes |
26 32 13.01 | Power Generation Diesel | Editorial changes |
26 32 13.02 | Power Generation to 30 kW | Editorial changes |
26 32 13.03 | Installation of Electric Power Generating Equipment | Editorial changes |
26 32 13.04 | Diesel Electric Generating Units (Liquid Cooled) | Editorial changes |
26 32 13.05 | Diesel Electric Generating Units (Air Cooled) | Editorial changes |
26 32 13.07 | Diesel Electric Generating Units Appendix B Factory Test | Editorial changes |
26 33 16 | Battery Racks | Editorial changes |
26 33 43 | Battery Chargers | Editorial changes |
26 33 53 | Static Uninterruptible Power Supply | Editorial changes |
26 50 00 | Lighting | Editorial changes |
26 52 00.01 | Lighting - Central Emergency System | Editorial changes |
26 52 13.13 | Emergency Lighting | Editorial changes |
26 52 13.16 | Exit Signs | Editorial changes |
31 09 16.01 | Pile Driving Templates | Editorial changes |
31 62 16.16 | Steel H Piles | Editorial changes |
31 62 16.19 | Unfilled Tubular Steel Piles | Editorial changes |
31 62 19 | Timber Piles | Editorial changes |
32 12 16.02 | Asphalt Paving for Building Sites | Editorial changes |
32 12 36.16 | Coal Tar Seal Coats | Editorial changes |
33 14 16 | Site Water Utility Distribution Piping | Editorial changes |
NMS summary of updates 2021-10
The 2021-10 NMS publication includes:
- New sections:
- Section 01 35 13.93 – Special project procedures during COVID-19 pandemic, to reduce the risk of exposure during construction.
- Section 01 57 00 – Temporary controls, specifying the installation of temporary erosion and sediment control measures' installation during Work Execution to prevent soil, groundwater and waterway pollution.
- Section 07 81 23 – Intumescent Fire Protection, for preparation and application procedures of thin film spray-on intumescent fire-resistant materials.
- Technical updates:
- Seven Sections in Division 04 – Masonry, to integrate Canadian Heritage conservation work practices.
- Three Sections in Division 07 – Thermal and Moisture Protection, to incorporate sustainable construction requirements, such as low carbon, water, materials, plastics, and construction waste disposal.
- Six Sections in Division 09 – Finishes, to incorporate current flooring construction techniques.
- Revisions:
- Four Sections in Division 31 – Earthwork, and two sections in Division 34 – Transportation, to integrate the requirements of temporary erosion and sediment control measures on-site during Execution of Work.
Technical updates
Section | Title | Status |
---|---|---|
01 35 13.93 | Special Project Procedures during COVID-19 Pandemic | New |
01 57 00 | Temporary Controls | New |
02 41 16 | Structure Demolition | Editorial changes |
02 41 16.09 | Structure Demolition - Short Form | Editorial changes |
03 11 19 | Insulating Concrete Forms | Editorial changes |
03 45 00 | Precast Architectural Concrete | Editorial changes |
03 48 00 | Precast Concrete Specialties | Editorial changes |
04 03 01.13 | Period Masonry Cleaning | Updated |
04 03 05.13 | Period Masonry Mortaring | Updated |
04 03 05.16 | Period Masonry Grouting | Updated |
04 03 05.21 | Period Masonry Repointing | Updated |
04 03 43.13 | Period Stone Repairing | Updated |
04 03 43.16 | Period Stone Replacing | Updated |
04 03 43.19 | Period Stone Dismantling | Updated |
06 08 99 | Rough Carpentry for Minor Works | Editorial changes |
06 10 53 | Miscellaneous Rough Carpentry | Updated |
06 14 00 | Treated Wood Foundations | Updated |
07 03 61.21 | Period Copper Sheet Roof Repair | Updated |
07 03 61.24 | Period Copper Sheet Roof Replacing | Updated |
07 21 26.13
Formerly: 07 21 29.13 |
Blown Insulation - Cellulose
Formerly: Blown insulation - cellulose |
Renumbered |
07 81 23 | Intumescent Fire Protection | New |
09 65 00.08 | Resilient Flooring for Minor Works | Updated |
09 65 19 | Resilient Tile Flooring | Updated |
09 66 13 | Portland Cement Terrazzo Flooring | Updated |
09 68 13 | Tile Carpeting | Updated |
09 68 16 | Sheet Carpeting | Updated |
09 96 66 | Aggregate Wall Coatings | Updated |
13 34 19 | Metal Building Systems | Editorial changes |
31 00 99 | Earthwork for Minor Works | Updated |
31 11 00 | Clearing and Grubbing | Updated |
31 23 33.01 | Excavating, Trenching and Backfilling | Updated |
31 32 19.13 | Geogrid Soil Stabilization | Updated |
32 01 13.02 | Flexible Paving Surface Treatment - Multiple Application | Editorial changes |
32 11 16.01 | Granular Sub-Base | Editorial changes |
32 11 23 | Aggregate Base Courses | Editorial changes |
32 12 16 | Asphalt Paving | Editorial changes |
32 12 16.02 | Asphalt Paving for Building Sites | Editorial changes |
32 13 13.17 | Roller Compacted Concrete Paving | Editorial changes |
32 15 60 | Roadway Dust Control | Editorial changes |
32 31 13 | Chain Link Fences and Gates | Editorial changes |
32 31 26 | Wire Fences and Gates | Editorial changes |
32 32 26 | Metal Crib Retaining Walls | Editorial changes |
32 91 19.13 | Topsoil Placement and Grading | Editorial changes |
32 91 19.16 | Topsoil Placement for Vegetated Roofs | Editorial changes |
32 93 10 | Trees, Shrubs and Ground Cover Planting | Editorial changes |
33 31 11 | Public Sanitary Sewerage Gravity Piping | Editorial changes |
34 71 13.25 | Vehicle W-Beam Guide Rail | Updated |
34 71 13.28 | Vehicle Box Beam Guide Rail | Updated |
NMS summary of updates 2021‑07
The 2021‑07 NMS publication includes:
- New sections that specify requirements for the commissioning of fire suppression, plumbing, HVAC and electrical systems:
- Section 21 08 00 - Commissioning of Fire Suppression
- Section 22 08 00 - Commissioning of Plumbing
- Section 23 08 00 - Commissioning of HVAC
- Section 26 08 00 - Commissioning of Electrical
- Updates to division 06 – Wood, Plastics and Composites, including a new Section 06 17 00 - Shop‑Fabricated Structural Wood that specifies technical requirements for shop‑fabricated structural wood components.
- New reference guides:
- Mass Timber and Shop‑Fabricated Structural Wood, which introduces Encapsulated Mass Timber Construction (EMTC) systems.
- Wood Treatment, which describes different pressure treatment methods that are applicable to provide protection against the effects of moisture, biological degradation and fire as they are applied to wood and mass timber products.
- Quality assurance and Quality control:
- New Section 01 43 00 – Quality Assurance: Specifies administrative and procedural requirements to ensure building code compliance and conformance to Contract Documents before and during Execution of Work.
- Revision to Section 01 45 00 – Quality control: To highlight the administrative and procedural requirements to ensure Contract Documents conformance during Work Execution.
- Revisions to a large number of Sections to integrate the changes related to the Section on Quality control and Quality Assurance.
- Technical updates to a number of sections in DIV02 and DIV06 to ensure the integration of Canadian Heritage conservation work practices.
- Revisions to Section 01 73 00 - Execution; to include common application/erection/installation and bracing/anchoring requirements to execute the Work.
Technical updates
Section | Title | Status |
---|---|---|
01 33 00 | Submittal Procedures | Editorial changes |
01 35 21 | LEED Requirements | Editorial changes |
01 35 43.10 | Environmental Procedures - Bridges | Editorial changes |
01 41 00 | Regulatory Requirements | Editorial changes |
01 43 00 | Quality Assurance | New |
01 45 00 | Quality Control | Updated |
01 73 00 | Execution | Updated |
01 74 19 | Waste Management and Disposal | Editorial changes |
01 78 00 | Closeout Submittals | Editorial changes |
01 79 00 | Demonstration and Training | Editorial changes |
02 03 43 | Period Structure Relocating | Updated |
02 03 44 | Shoring and Support of Period Structures | Updated |
02 50 00 | Site Remediation | Editorial changes |
02 83 10 | Lead-Base Paint Abatement - Minimum Precautions | Editorial changes |
02 83 11 | Lead-Base Paint Abatement - Intermediate Precautions | Editorial changes |
02 83 12 | Maximum Precautions | Editorial changes |
02 84 00 | Polychlorinate Biphenyl Remediation | Editorial changes |
03 01 36 | Epoxy Injection/Chemical Grout | Editorial changes |
03 01 37 | Concrete Restoration | Editorial changes |
03 01 41 | Precast Concrete Cleaning: Water Pressure Method | Editorial changes |
03 10 00 | Concrete Forming and Accessories | Editorial changes |
03 11 19 | Insulating Concrete Forms | Editorial changes |
03 20 00 | Concrete Reinforcing | Editorial changes |
03 30 00 | Cast-In-Place Concrete | Editorial changes |
03 30 00.09 | Cast-In-Place Concrete - Short Form | Editorial changes |
03 31 23.13 | High-Performance Structural Concrete for Bridge Decks | Editorial changes |
03 35 00 | Concrete Finishing | Editorial changes |
03 35 46 | Concrete Floor Hardening | Editorial changes |
03 37 13 | Shotcrete | Editorial changes |
03 41 00 | Precast Structural Concrete | Editorial changes |
03 41 36 | Precast Structural Post-Tensioned Concrete | Editorial changes |
03 45 00 | Precast Architectural Concrete | Editorial changes |
03 60 10 | Pressure Grouting Rock | Editorial changes |
04 03 05.13 | Period Masonry Mortaring | Editorial changes |
04 03 21.19 | Clay Brick Conservation Treatment | Editorial changes |
04 03 21.26 | Period Glazed Structural Clay Facing Tile Repair | Editorial changes |
04 03 43.13 | Period Stone Repairing | Editorial changes |
04 03 43.16 | Period Stone Replacing | Editorial changes |
04 03 43.19 | Period Stone Dismantling | Editorial changes |
04 05 00 | Common Work Results for Masonry | Editorial changes |
04 20 00.08 | Masonry for Minor Works | Editorial changes |
04 43 13 | Marble Veneer Cladding | Editorial changes |
04 43 16 | Granite Veneer Cladding | Editorial changes |
04 43 19 | Collected Stone Veneer Cladding | Editorial changes |
04 43 23 | Quarried Stone Veneer Cladding | Editorial changes |
04 43 26 | Dimension Stone Veneer Cladding | Editorial changes |
04 71 13.13 | Prefaced Calcium Silicate Manufactured Brick Masonry | Editorial changes |
05 12 23 | Structural Steel for Buildings | Editorial changes |
05 12 33 | Structural Steel for Bridges | Editorial changes |
05 14 00 | Structural Aluminum for Buildings | Editorial changes |
05 21 00 | Steel Joist Framing | Editorial changes |
05 31 00 | Steel Decking | Editorial changes |
05 41 00 | Structural Metal Stud Framing | Editorial changes |
06 00 00.RG.01 | Division 06 Reference Guide - Wood Treatment | New |
06 00 00.RG.02 | Division 06 Reference Guide - Mass Timber and Shop Fabricated Structural Wood | New |
06 03 05.73 | Long-Term Period Wood Treatment | Updated |
06 03 13 | Conservation Treatment of Period Log Construction | Updated |
06 03 13.23 | Conservation Treatment of Period Heavy Timber | Updated |
06 03 50.13 | Carvel Planking | Editorial changes |
06 03 50.16 | Steam Bending and Replacement of Curved Wood Members | Editorial changes |
06 05 73 | Wood Treatment | Updated |
06 08 99 | Rough Carpentry for Minor Works | Updated |
06 15 00 | Wood Decking | Updated |
06 17 00 | Shop‑Fabricated Structural Wood | New |
06 17 53 | Shop-Fabricated Wood Trusses | Updated |
06 18 00 | Glued-Laminated Construction | Updated |
06 20 00 | Finish Carpentry | Editorial changes |
06 40 00 | Architectural Woodwork | Editorial changes |
06 40 23.13 | Plastic Laminate Finishing for Interior Architectural Woodwork | Editorial changes |
07 03 30.13 | Conservation Treatment for Period Canvas Roofing | Editorial changes |
07 03 30.16 | Conservation Treatment for Period Board Roofing | Editorial changes |
07 03 31.26 | Conservation Treatment for Period Slate Shingles | Editorial changes |
07 03 31.29 | Conservation Treatment for Period Wood Shingles and Shakes | Editorial changes |
07 03 32.16 | Conservation Treatment for Period Concrete Roof Tiles | Editorial changes |
07 03 33.13 | Conservation Treatment for Period Sod Roofing | Editorial changes |
07 03 41.13 | Conservation Treatment for Period Metal Roof Panels | Editorial changes |
07 03 61.21 | Period Copper Sheet Roof Repair | Editorial changes |
07 08 13 | Building Enclosure Performance Testing | Editorial changes |
07 12 13 | Built-Up Asphalt Waterproofing | Editorial changes |
07 13 52 | Modified Bituminous Sheet Waterproofing | Updated |
07 13 53 | Elastomeric Sheet Waterproofing | Editorial changes |
07 14 13 | Hot Fluid-Applied Rubberized Asphalt Waterproofing | Editorial changes |
07 16 19 | Metal Oxide Waterproofing | Editorial changes |
07 17 13 | Bentonite Panel Waterproofing | Editorial changes |
07 18 00 | Traffic Coatings | Editorial changes |
07 19 00 | Water Repellents | Editorial changes |
07 21 13 | Board Insulation | Editorial changes |
07 21 16 | Blanket Insulation | Editorial changes |
07 21 23 | Loose - Fill Insulation | Editorial changes |
07 21 26.13
Formerly: 07 21 29.13 |
Blown Insulation – Cellulose
Formerly: Blown Insulation - Cellulose |
Renumbered and Editorial changes |
07 21 26.16 | Blown Insulation - Mineral Fibre | Editorial changes |
07 21 29 | Sprayed Insulation - Polyurethane Foam | Editorial changes |
07 24 00 | Exterior Insulation and Finish Systems | Editorial changes |
07 24 10.01 | Exterior Insulation and Finish Systems - Panelized | Editorial changes |
07 24 10.03 | Exterior Finish - Direct Applied | Editorial changes |
07 26 00 | Vapour Retarders | Editorial changes |
07 27 00.01 | Air Barriers - Descriptive or Proprietary | Editorial changes |
07 27 00.02 | Air Barriers - Performance | Editorial changes |
07 31 13 | Asphalt Shingles | Editorial changes |
07 31 29 | Wood Shingles and Shakes | Editorial changes |
07 42 13.23 | Metal Composite Material Wall Panels | Editorial changes |
07 42 43 | Composite Wall Panels | Editorial changes |
07 42 46 | Fibre Reinforced Cementitious Wall Panels | Editorial changes |
07 46 16 | Aluminum Siding | Editorial changes |
07 46 19 | Steel Siding | Editorial changes |
07 46 23 | Wood Siding | Editorial changes |
07 46 33 | Plastic Siding | Editorial changes |
07 51 00 | Built-Up Bituminous Roofing | Editorial changes |
07 53 23 | Ethylene Propylene Diene Monomer Roofing | Editorial changes |
07 54 19 | Polyvinyl Chloride Roofing | Editorial changes |
07 55 63 | Vegetated Protected Membrane Roofing | Editorial changes |
07 56 13 | Hot Fluid Applied Rubberized Asphalt Roofing | Editorial changes |
07 61 00 | Sheet Metal Roofing | Editorial changes |
07 62 00 | Sheet Metal Flashing and Trim | Editorial changes |
07 72 33 | Roof Hatches | Editorial changes |
07 81 00 | Applied Fireproofing | Editorial changes |
07 84 00 | Fire Stopping | Editorial changes |
07 95 13 | Expansion Joint Cover Assemblies | Editorial changes |
08 03 11 | Historic - Period Wood Doors | Editorial changes |
08 03 14.33 | Conservation Treatment for Period Stile and Rail Wood Doors | Editorial changes |
08 03 51.23 | Conservation Treatment for Period Steel Windows | Editorial changes |
08 03 52 | Conservation Treatment for Period Wood Windows | Editorial changes |
08 11 16 | Aluminum Doors and Frames | Editorial changes |
08 11 19 | Stainless-Steel Doors and Frames | Editorial changes |
08 13 73 | Sliding Metal Doors | Editorial changes |
08 14 16 | Flush Wood Doors | Editorial changes |
08 14 73 | Sliding Wood and Plastic Doors | Editorial changes |
08 31 00 | Access Doors and Panels | Editorial changes |
08 33 00 | Overhead Coiling Doors and Grilles | Editorial changes |
08 33 13 | Coiling Counter Doors | Editorial changes |
08 33 36 | Side Coiling Grilles | Editorial changes |
08 34 59.13 | Vault Doors and Frames | Editorial changes |
08 36 19 | Multi-Leaf Vertical Lift Doors | Editorial changes |
08 42 26.33 | Swinging All Glass Entrances | Editorial changes |
08 42 29 | Automatic Entrances | Editorial changes |
08 44 13 | Glazed Aluminum Curtain Walls | Editorial changes |
08 44 23 | Structural Sealant Glazed Curtain Walls | Editorial changes |
08 50 00 | Windows | Editorial changes |
08 62 00 | Unit Skylights | Editorial changes |
08 71 00 | Door Hardware | Editorial changes |
08 80 00 | Glazing | Editorial changes |
08 90 00 | Louvres and Vents | Editorial changes |
09 01 90.62 | Exterior Repainting | Editorial changes |
09 01 90.63 | Interior Repainting | Editorial changes |
09 03 25 | Conservation Treatment for Period Plastering | Editorial changes |
09 03 91.13 | Conservation Treatment for Period Exterior Painting | Editorial changes |
09 03 91.23 | Conservation Treatment for Period Interior Painting | Editorial changes |
09 21 16.08 | Gypsum Board Assemblies for Minor Works | Editorial changes |
09 51 13 | Acoustical Panel Ceilings | Editorial changes |
09 54 23 | Linear Metal Ceilings | Editorial changes |
09 64 23 | Wood Parquet Flooring | Editorial changes |
09 64 29 | Wood Strip and Plank Flooring | Editorial changes |
09 64 53 | Resilient Wood Flooring Assemblies | Editorial changes |
09 65 00.08 | Resilient Flooring for Minor Works | Editorial changes |
09 65 16 | Resilient Sheet Flooring | Editorial changes |
09 65 19 | Resilient Tile Flooring | Editorial changes |
09 66 13 | Portland Cement Terrazzo Flooring | Editorial changes |
09 66 16 | Terrazzo Floor Tile | Editorial changes |
09 66 23 | Resinous Matrix Terrazzo Flooring | Editorial changes |
09 68 13 | Tile Carpeting | Editorial changes |
09 72 16 | Vinyl-Coated Fabric Wall Coverings | Editorial changes |
09 80 00 | Acoustic Treatment | Editorial changes |
09 91 13 | Exterior Painting | Editorial changes |
09 91 23 | Interior Painting | Editorial changes |
09 96 59 | High-Build Glazed Coatings | Editorial changes |
09 96 66 | Aggregate Wall Coatings | Editorial changes |
10 21 13.13 | Metal Toilet Compartments | Editorial changes |
10 22 13 | Wire Mesh Partitions | Editorial changes |
10 22 19.54 | Demountable Partitions - Post and Panel | Editorial changes |
10 22 19.55 | Demountable Partitions - Stud Type | Editorial changes |
10 22 39 | Folding Panel Partitions | Editorial changes |
10 44 00 | Fire Protection Specialties | Editorial changes |
11 13 19.13 | Loading Dock Levelers | Editorial changes |
11 13 19.23 | Loading Dock Lifts | Editorial changes |
11 40 10 | Food Service Stock Equipment | Editorial changes |
11 41 23 | Walk-In Coolers and Freezers | Editorial changes |
11 51 23.13 | Metal Library Shelving | Editorial changes |
11 53 13 | Laboratory Fume Hoods | Editorial changes |
12 21 16 | Vertical Louvre Blinds | Editorial changes |
12 35 39 | Commercial Kitchen Casework | Editorial changes |
14 20 03 | Freight Elevators | Editorial changes |
14 20 06 | Passenger Elevators | Editorial changes |
21 08 00 | Commissioning of Fire Suppression | New |
21 30 00 | Fire Pumps | Editorial changes |
22 08 00 | Commissioning of Plumbing | New |
23 05 19 | Meters and Gauges for HVAC Piping | Editorial changes |
23 05 19.13 | Thermometers and Pressure Gauges - Piping Systems | Editorial changes |
23 05 93.13 | Testing, Adjusting and Balancing of Fume Hoods | Editorial changes |
23 07 13 | Duct Insulation | Editorial changes |
23 08 00 | Commissioning of HVAC | New |
23 52 00 | Heating Boilers | Editorial changes |
23 54 13 | Electric-Resistance Furnaces | Editorial changes |
23 54 16 | Fuel-Fired Furnaces | Editorial changes |
23 57 00 | Heat Exchangers for HVAC | Editorial changes |
23 64 13 | Absorption Water Chillers | Editorial changes |
23 64 16 | Centrifugal Water Chillers | Editorial changes |
23 64 19 | Reciprocating Water Chillers | Editorial changes |
23 64 26 | Rotary-Screw Water Chillers | Editorial changes |
23 65 16 | Natural Draft Cooling Towers | Editorial changes |
23 72 00 | Air-To-Air Energy Recovery Equipment | Editorial changes |
23 73 00.13 | Air Handling - Built-Up | Editorial changes |
23 73 00.16 | Air Handling Units - Packaged | Editorial changes |
23 74 00 | Packaged Outdoor HVAC Equipment | Editorial changes |
23 81 23 | Computer Room Air Conditioning | Editorial changes |
23 81 40 | Air and Water Source Unitary Heat Pumps | Editorial changes |
26 05 14 | Power Cable and Overhead Conductors (1001 V) | Editorial changes |
26 05 27 | Grounding - Primary | Editorial changes |
26 05 33.01 | Surface and Lighting Fixture Raceways | Editorial changes |
26 08 00 | Commissioning of Electrical | New |
26 09 23.03 | Lighting Control Devices - Incandescent Dimming | Editorial changes |
26 11 00.01 | Outdoor Substation to 15 kV | Editorial changes |
26 12 13 | Liquid Filled, Medium Voltage Transformers | Editorial changes |
26 12 19 | Pad Mounted, Liquid Filled, Medium Voltage Transformers | Editorial changes |
26 12 21 | Transformer Vault Equipment to 15 kV | Editorial changes |
26 27 19 | Multi-Outlet Assemblies | Editorial changes |
26 35 33 | Power Factor Correction Equipment | Editorial changes |
26 42 00.01 | Telethermics - Cathodic Protection | Editorial changes |
26 50 00 | Lighting | Editorial changes |
26 52 13.16 | Exit Signs | Editorial changes |
31 31 19.13 | Chemical Vegetation Control | Editorial changes |
31 53 13 | Timber Cribwork | Editorial changes |
32 11 33 | Cement-Treated Base Courses | Editorial changes |
32 14 13 | Precast Concrete Unit Paving | Editorial changes |
33 05 16 | Maintenance Holes and Catch Basin Structures | Editorial changes |
33 65 16 | Telethermics - Distribution Piping - PVC - FRP | Editorial changes |
33 65 26 | Telethermics - Insulated and Plastic Jacketted Systems | Editorial changes |
33 65 33 | Telethermics - Dryable Drainable, Testable Conduit Systems | Editorial changes |
33 65 43 | Telethermics - Steel Tunnel Systems | Editorial changes |
33 65 46 | Telethermics - Shallow Inverted Trench (SIT) Systems | Editorial changes |
33 65 73 | Concrete Encased Duct Banks and Manholes | Editorial changes |
33 65 76 | Direct Buried Underground Cable Ducts | Editorial changes |
33 71 16.01 | Electrical Pole Lines and Hardware | Editorial changes |
33 71 73.01 | Overhead Electrical Service | Editorial changes |
33 71 73.02 | Underground Electrical Service | Editorial changes |
34 43 13.16 | Airfield Runway and Taxiway Inset Lighting | Editorial changes |
34 72 16 | Railway Siding | Editorial changes |
NMS summary of updates 2021-01
The 2021-01 NMS publication includes:
Master performance and design specifications: 102 specifications are now organized by major building functional elements using the UniFormatTM classification system. References for energy efficient and net zero operational carbon building design and operation were introduced into 37 Sections across Elements B and D to G.
Updates to master prescriptive specification Sections include:
- Incorporated guidance on thermal resilience into 9 Sections across Divisions 04 and 07.
- Updated Division 01 and Division 03 Sections with requirements for Environmental Product Declarations (EPDs) to demonstrate life-cycle assessment of embodied carbon in construction materials.
- Integrated sustainability requirements into 15 Sections in Division 01 for aspects such as low carbon, water, materials, plastics, and construction waste disposal in projects.
- Updated 3 sections on resilient flooring from Division 09 to meet current industry standards and best practices, and to improve cross-trade coordination.
- Edited acronyms and references in 3 sections in Divisions 01, 08 and 09.
Technical updates
Section | Title | Status |
---|---|---|
1020 | Project Brief | New |
1030 | Project Criteria | New |
1040 | Existing Conditions | New |
A1010 | Standard Foundations | New |
A1020 | Special Foundations | New |
A2010 | Walls for Subgrade Enclosures | New |
A4010 | Standard Slabs-On-Grade | New |
A4020 | Structural Slabs-On-Grade | New |
A4030 | Slab Trenches | New |
A4040 | Pits and Bases | New |
A4090 | Slab-On-Grade Supplementary Components | New |
A6010 | Building Subdrainage | New |
A6020 | Off-Gassing Mitigation | New |
A9010 | Substructure Excavation | New |
A9020 | Construction Dewatering | New |
A9030 | Excavation Support | New |
A9040 | Soil Treatment | New |
B1010 | Floor Construction | New |
B1020 | Roof Construction | New |
B1080 | Stairs | New |
B2010 | Exterior Walls | New |
B2020 | Exterior Windows | New |
B2050 | Exterior Doors and Grilles | New |
B2080 | Exterior Wall Appurtenances | New |
B2090 | Exterior Wall Specialties | New |
B3010 | Roofing | New |
B3020 | Roof Appurtenances | New |
B3040 | Traffic Bearing Horizontal Enclosures | New |
B3060 | Horizontal Openings | New |
B3080 | Overhead Exterior Enclosures | New |
C1010 | Interior Partitions | New |
C1020 | Interior Windows | New |
C1030 | Interior Doors | New |
C1040 | Interior Grilles and-Gates | New |
C1060 | Raised Floor Construction | New |
C1070 | Suspended Ceiling Construction | New |
C1090 | Interior Specialties | New |
C2010 | Wall Finishes | New |
C2020 | Interior Fabrications | New |
C2030 | Flooring | New |
C2040 | Stair Finishes | New |
C2050 | Ceiling Finishes | New |
D1010 | Vertical Conveying Systems | New |
D2010 | Domestic Water Distribution | New |
D2020 | Sanitary Drainage | New |
D2030 | Building Support Plumbing Systems | New |
D2050 | General Service Compressed-Air | New |
D3010 | Facility Fuel Systems | New |
D3020 | Heating Systems | New |
D3030 | Cooling Systems | New |
D3050 | Facility HVAC Distribution Systems | New |
D3060 | Ventilation | New |
D4010 | Fire Suppression | New |
D4030 | Fire Protection Specialties | New |
D5020 | Electrical Service and Distribution | New |
D5030 | General Purpose Electrical Power | New |
D5040 | Lighting | New |
D5080 | Miscellaneous Electrical Systems | New |
D6010 | Data Communications | New |
D6060 | Distributed Communications and Monitoring | New |
D7010 | Access Control and Intrusion Detection | New |
D7030 | Electronic Surveillance | New |
D7050 | Detection and Alarm | New |
D8010 | Integrated Automation Facility Controls | New |
E1010 | Vehicle and Pedestrian Equipment | New |
E1030 | Commercial Equipment | New |
E1040 | Institutional Equipment | New |
E1060 | Residential Equipment | New |
E1070 | Entertainment and Recreational Equipment | New |
E1090 | Other Equipment | New |
E2010 | Fixed Furnishings | New |
E2050 | Movable Furnishings | New |
F1010 | Integrated Construction | New |
F1020 | Special Structures | New |
F1030 | Special Function Construction | New |
F1050 | Special Facility Components | New |
F1060 | Athletic and Recreational Special Construction | New |
F1080 | Special Instrumentation | New |
F2010 | Hazardous Materials Remediation | New |
F3030 | Selective Demolition | New |
G1010 | Site Clearing | New |
G1020 | Site Elements Demolition | New |
G1030 | Site Element Relocation | New |
G1050 | Site Remediation | New |
G1070 | Site Earthwork | New |
G2010 | Roadways | New |
G2020 | Parking Lots | New |
G2030 | Pedestrian Plazas and Walkways | New |
G2040 | Airfields | New |
G2050 | Athletic Recreational and Playfield Areas | New |
G2060 | Site Development | New |
G2080 | Landscaping | New |
G3010 | Water Utilities | New |
G3020 | Sanitary Sewerage Utilities | New |
G3030 | Storm Drainage Utilities | New |
G3050 | Site Energy Distribution | New |
G3060 | Site Fuel Distribution | New |
G4010 | Site Electrical Distribution Systems | New |
G4050 | Site Lighting | New |
G5010 | Site Communications Systems | New |
G9010 | Tunnels | New |
Z1040 | Quality Requirements | New |
01 14 25 | Designated Substances Report | Editorial changes |
01 33 29 | Sustainable Design Reporting | Updated |
01 35 13.43 | Special Project Procedures for Contaminated Sites | Editorial changes |
01 35 21 | LEED Requirements | Editorial changes |
01 35 43.10 | Environmental Procedures - Bridges | Editorial changes |
01 41 00 | Regulatory Requirements | Editorial changes |
01 47 13 | Sustainable Requirements: Concept Design | Editorial changes |
01 47 15 | Sustainable Requirements: Construction | Editorial changes |
01 47 19 | Sustainable Requirements: Operation | Editorial changes |
01 50 13 | Temporary Facilities and Controls for Dredging | Editorial changes |
01 51 00 | Temporary Utilities | Editorial changes |
01 52 00 | Construction Facilities | Editorial changes |
01 56 00 | Temporary Barriers and Enclosures | Editorial changes |
01 61 00 | Common Product Requirements | Editorial changes |
01 74 00 | Cleaning | Editorial changes |
01 74 19 | Waste Management and Disposal | Editorial changes |
01 74 19.13 | Carpet Reclamation | Editorial changes |
02 03 43 | Period Structure Relocating | Updated |
02 50 00 | Site Remediation | Updated |
03 01 36 | Epoxy Injection/Chemical Grout | Updated |
03 01 37 | Concrete Restoration | Updated |
03 10 00 | Concrete Forming and Accessories | Updated |
03 11 19 | Insulating Concrete Forms | Updated |
03 20 00 | Concrete Reinforcing | Updated |
03 30 00 | Cast-In-Place Concrete | Updated |
03 30 00.09 | Cast-In-Place Concrete - Short Form | Updated |
03 31 23.13 | High-Performance Structural Concrete for Bridge Decks | Editorial changes |
03 35 00 | Concrete Finishing | Updated |
03 35 46 | Concrete Floor Hardening | Updated |
03 37 13 | Shotcrete | Updated |
03 37 26 | Underwater Placed Concrete | Updated |
03 41 00 | Precast Structural Concrete | Editorial changes |
03 41 36 | Precast Structural Post-Tensioned Concrete | Editorial changes |
03 45 00 | Precast Architectural Concrete | Editorial changes |
03 48 00 | Precast Concrete Specialties | Updated |
03 60 10 | Pressure Grouting Rock | Editorial changes |
04 43 19 | Collected Stone Veneer Cladding | Editorial changes |
04 43 23 | Quarried Stone Veneer Cladding | Editorial changes |
04 43 26 | Dimension Stone Veneer Cladding | Editorial changes |
07 08 13 | Building Enclosure Performance Testing | Editorial changes |
07 46 16 | Aluminum Siding | Editorial changes |
07 46 19 | Steel Siding | Editorial changes |
07 46 23 | Wood Siding | Editorial changes |
07 46 33 | Plastic Siding | Editorial changes |
07 61 00 | Sheet Metal Roofing | Editorial changes |
07 92 00 | Joint Sealants | Editorial changes |
08 90 00 | Louvres and Vents | Editorial changes |
09 03 25 | Conservation Treatment for Period Plastering | Editorial changes |
09 65 00.08 | Resilient Flooring for Minor Works | Updated |
09 65 16 | Resilient Sheet Flooring | Updated |
09 65 19 | Resilient Tile Flooring | Updated |
NMS summary of updates 2019-10
The 2019-10 NMS publication includes:
- Update to corrosion protective coating requirements including certification requirements for coating application specialists per ANSI/NACE No.13/SSPC-ASC-1-2016-SG.
- Update to Sections on concrete and masonry
Technical updates
Section | Title | Status |
---|---|---|
01 45 00 | Quality Control | Updated |
02 83 10 | Lead-Base Paint Abatement - Minimum Precautions | Updated |
02 83 11 | Lead-Base Paint Abatement - Intermediate Precautions | Updated |
02 83 12 | Lead-Base Paint Abatement - Maximum Precautions | Updated |
03 01 37 | Concrete Restoration | Updated |
03 35 00 | Concrete Finishing | Updated |
03 37 13 | Shotcrete | Updated |
03 45 00 | Precast Architectural Concrete | Updated |
04 43 19 | Collected Stone Veneer Cladding | Updated |
04 43 23 | Quarried Stone Veneer Cladding | Updated |
04 43 26 | Dimension Stone Veneer Cladding | Updated |
05 12 23 | Structural Steel for Buildings | Updated |
05 12 33 | Structural Steel for Bridges | Updated |
05 14 00 | Structural Aluminum for Buildings | Updated |
05 21 00 | Steel Joist Framing | Updated |
05 31 00 | Steel Decking | Updated |
05 41 00 | Structural Metal Stud Framing | Updated |
05 50 00 | Metal Fabrications | Updated |
05 51 00 | Metal Stairs and Ladders | Updated |
05 52 16 | Modular Workplace Guardrail System | Updated |
09 01 90.62 | Exterior Repainting | Updated |
09 01 90.63 | Interior Repainting | Updated |
09 91 00.08 | Painting for Minor Works | Updated |
09 91 13 | Exterior Painting | Updated |
09 91 13.23 | Exterior Painting of Structural Steel | Updated |
09 96 53 | Elastomeric Coatings | Updated |
09 96 59 | High-Build Glazed Coatings | Updated |
33 56 13 | Aboveground Fuel - Storage Tanks | Updated |
33 56 16 | Underground Fuel - Storage Tanks | Updated |
33 65 13 | Telethermics - Distribution Piping - Steel | Updated |
44 41 13 | Commercial Water Treatment Plants | Updated |
NMS summary of updates 2019-04
The 2019-04 NMS publication includes:
- Sections in Division 32, to reflect the requirements of the new Canadian Landscape Standard (CLS) and the revised Canadian Nursery Stock Standard (CNSS).
Technical updates
Section | Title | Status |
---|---|---|
01 35 43 | Environmental procedures | Updated |
01 35 43.10 | Environmental procedures - bridges | New |
04 03 01.13 | Period masonry cleaning | Editorial edits |
07 21 23 | Loose - fill insulation | Editorial edits |
07 21 29.13
Formerly: 07 21 29.01 |
Blown insulation - cellulose
Formerly: Blown insulation - cellulose |
Renumbered and updated |
07 92 00 | Joint sealants | Updated |
32 01 90.23 | Pruning | Updated |
32 01 90.33 | Tree and shrub preservation | Updated |
32 91 19.13 | Topsoil placement and grading | Updated |
32 91 19.16
Formerly: 32 91 19.14 |
Topsoil placement for vegetated roofs
Formerly: Topsoil placement for vegetated roofs |
Renumbered and updated |
32 93 10 | Trees, shrubs and ground cover planting | Updated |
32 93 23.13 | Interior plantings | Updated |
35 01 40.92 | Preservation of water courses and wetlands | Updated |
NMS summary of updates 2019-01
The 2019-01 NMS publication includes:
- The Prohibition of Asbestos and Products Containing Asbestos Regulations as they were published in Canada Gazette, Part II, on October 17, 2018. Reference to this regulation was added to NMS Sections in DIV01, DIV02, DIV07, DIV23 and DIV33.
- Revised Section 01 35 21 – LEED requirements, reflecting current sustainability requirements for renewable energy and regionally manufactured materials, recycled content and low-emitting materials.
- The addition of new NMS Section 07 08 13 – Building Enclosure Performance Testing, which includes general commissioning and verification procedures to support quality assurance for delivering high-performance building envelopes and for performing whole building air tightness testing.
- Updating technical content in DIV31 and DIV32, adding references to the new requirements of the Canadian Landscape Standard (CLS) and the Canadian Nursery Stock Standard (CNSS).
Technical updates
Section | Title | Status |
---|---|---|
01 35 13.43 | Special Project Procedures for Contaminated Sites | Updated |
01 35 21 | Leed requirements | Updated |
01 41 00 | Regulatory requirements | Updated |
02 82 00.01 | Asbestos Abatement - Minimum Precautions | Updated |
02 82 00.02 | Asbestos Abatement - Intermediate Precautions | Updated |
02 82 00.03 | Asbestos Abatement - Maximum Precautions | Updated |
07 03 31.29 | Conservation treatment for Period Wood Shingles and Shakes | Updated |
07 08 13 | Building Enclosure Performance Testing | New |
07 21 26.16 | Blown Insulation – Mineral Fibre | Updated |
07 21 29
Formerly: 07 21 29.03 |
Sprayed Insulation - Polyurethane Foam
Formerly: Sprayed Insulation - Polyurethane Foam |
Renumbered and Updated |
08 14 16 | Flush Wood Doors | Editorial edits |
23 82 16.14
Formerly: 23 55 13 |
Electric-Resistance Air Coils
Formerly: Fuel-Fired Duct Heaters |
Renumbered, Renamed and updated |
23 82 39.26 | Liquid Heaters | Updated |
31 11 00 | Clearing and Grubbing | Updated |
32 92 19.13 | Mechanical Seeding | Updated |
32 92 19.16 | Hydraulic Seeding | Updated |
32 92 23 | Sodding | Updated |
33 14 16 | Site Water Utility Distribution Piping | Updated |
33 31 11 | Public Sanitary Sewerage Gravity Piping | Updated |
33 31 23 | Sanitary Sewerage Force Main Piping | Updated |
33 41 00 | Storm Utility Drainage Piping | Updated |
33 46 13.01 | Foundation and Underslab Drainage | Updated |
NMS summary of updates 2018-10
The 2018-10 NMS publication includes updates across several construction industry sectors. References to the most current codes, standards and the Canadian Construction Documents Committee (CCDC) documents were modified. These updates are highlighted below:
- DIV01: updating three NMS sections to consistently communicate sustainability goals and requirements.
- DIV03: adding a new NMS section; Pressure Grouting Rock. Adopting the new certification requirements for precast concrete manufacturers to enhance quality assurance for climate resilient commercial buildings.
- DIV05, DIV07, DIV08 and DIV09: modifying the requirements for ECOLOGO® certified building materials, chemicals and plastics to reduce environmental impact due to construction activities.
Technical updates
Section | Title | Status |
---|---|---|
01 11 00 | Summary of Work | Updated |
01 21 00 | Allowances | Updated |
01 47 13 | Sustainable Requirements: Concept Design | Updated |
01 47 15 | Sustainable Requirements: Construction | Updated |
01 47 19 | Sustainable Requirements: Operation | Updated |
03 11 19 | Insulating concrete forms | Updated |
03 41 00 | Precast Structural Concrete | Updated |
03 60 10 | Pressure Grouting Rock | New |
05 50 00 | Metal Fabrications | Updated |
05 51 00 | Metal Stairs and Ladders | Updated |
07 03 61.21 | Period Copper Sheet Roof Repair | Updated |
08 11 19 | Stainless-Steel Doors and Frames | Updated |
09 22 16 | Non-Structural Metal Framing | Updated |
NMS summary of updates 2018-07
- Development of New Section 00 01 15 – List of Drawings Sheets; where the project's "Drawing Sheets" are to be listed in a unique manner that maintains contract documentation consistency throughout the Project Manual.
- Development of New Section 02 22 10 – Existing Building Conditions Assessment; this new Section underscores the importance of evaluating the existing building conditions before beginning retrofit work to improve energy efficiency or climate resiliency.
- Sustainability Requirements: A number of NMS Sections in DIV02, DIV04, DIV05, DIV06, DIV07, DIV08, DIV09 and DIV22, were updated to consistently communicate sustainability goals and requirements.
Technical updates
Section | Title | Status |
---|---|---|
00 01 07 | Seals Page | Updated |
00 01 10 | Table of Contents | Updated |
00 01 15 | List of Drawing Sheets | New |
00 11 19.53 | Request for Proposal - Design Build (Single Prime Contract) | Editorial Changes |
00 21 13 | Instructions to Bidders | Updated |
01 12 00 | Multiple Contract Summary | Updated |
01 29 83 | Payment Procedures for Testing Laboratory Services | Updated |
01 47 13 | Sustainable Requirements: Concept Design | Updated |
01 47 19 | Sustainable Requirements: Operation | Editorial Changes |
01 74 19 | waste management and disposal | Editorial Changes |
02 22 10 | Existing Building Condition Assessments | New |
02 41 19.13 | Selective Building Demolition | Updated |
02 41 19.16 | Selective Interior Demolition | Updated |
02 65 00 | Underground Storage Tank Removal | Updated |
03 30 00 | Cast-In-Place Concrete | Updated |
03 41 36 | Precast Structural Post-Tensioned Concrete | Updated |
03 45 00 | Precast architectural concrete | Updated |
04 03 43.13 | Period stone Repairing | Editorial Changes |
04 20 00.08 | Masonry for Minor Works | Updated |
04 71 13 | Calcium Silicate Manufactured Brick Masonry | Updated |
04 71 13.13 | Prefaced Calcium Silicate Manufactured Brick Masonry | Updated |
04 73 13 | Calcium Silicate Manufactured Stone Masonry | Updated |
05 52 16 | Modular Workplace Guardrail System | Updated |
06 05 73 | Wood Treatment | Updated |
06 08 99 | Rough Carpentry for Minor Works | Updated |
06 10 53 | Miscellaneous rough carpentry | Updated |
07 12 13 | Built-Up Asphalt Waterproofing | Updated |
07 42 46 | Fibre Reinforced Cementitious Wall Panels | Updated |
07 62 00 | Sheet Metal Flashing and Trim | Updated |
08 11 00 | Metal Doors and Frames | Updated |
08 11 19 | Stainless-Steel Doors and Frames | Updated |
08 11 69 | Metal Storm Doors and Frames | Updated |
08 13 73 | Sliding Metal Doors | Updated |
08 14 16 | Flush Wood Doors | Updated |
09 30 13 | Ceramic Tiling | Updated |
09 30 15 | Quarry and Paver Tiling | Updated |
09 51 13 | Acoustical Panel Ceilings | Updated |
09 66 23 | Resinous Matrix Terrazzo Flooring | Updated |
09 72 16 | Vinyl-Coated Fabric Wall Coverings | Updated |
09 80 00 | Acoustic Treatment | Updated |
09 91 00.08 | Painting for Minor Works | Updated |
09 96 59 | High-Build Glazed Coatings | Updated |
22 05 05 | Selective Demolition for Plumbing | Editorial Changes |
23 05 05 | Selective Demolition for Heating, Ventilating, and Air Conditioning (HVAC) | Editorial Changes |
26 05 05 | Selective Demolition for Electrical | Editorial Changes |
NMS summary of updates 2018-04
The 2018-04 NMS publication includes major updates to meet construction industry demands and incorporated current codes and standards. Highlights include:
- DIV01 and 02: adopting new regulations of Workplace Hazardous Materials Information System (WHMIS) 2015 for Safety Data Sheets (SDS) for hazardous products sold, distributed or imported into Canada which replace the Materials Safety Data Sheets (MSDS) format of previous WHMIS 1988 regulation. References across all NMS sections now reflect this change.
- DIV03: adding two new NMS sections; Concrete Restoration and Precast Concrete Cleaning: Water Pressure Method. Adoption of new certification requirements for precast concrete manufacturers to enhance quality assurance for climate resilient commercial and residential buildings, and to produce materials that are durable and can increase lifespan of structures.
- DIV04, 05, 06, 08, 09 and 33: updating technical standards and some editorial changes, such as reference standard names and Section reference numbers.
- DIV07: developing new technical content of Section 07 84 00 – Fire Stopping, and updating requirements across several dozen related NMS sections. Developed with the Firestop Contractors International Association (FCIA) to capture industry best practices, offer options for quality assurance and align terminology with industry and National Building Code of Canada 2015 (NBC). Includes industry recommended practices for certification, use of design listings and alternative solutions, fire stop inspection/validation and identification/documentation procedures of fire stop systems in construction projects. Technical updates of the renumbered Section 07 21 26.16 – Blown Insulation - Mineral Fibre, adding new administrative requirements and updating products and procedures in order to better capture industry best practices.
- Implementing unit soft conversion of imperial units to metric units for dimensions related to spacing of framing elements.
Technical updates
Section | Title | Status |
---|---|---|
03 01 37 | Concrete Restoration | New |
03 01 41 | Precast Concrete Cleaning: Water Pressure Method | New |
03 30 00 | Cast-In-Place Concrete | Updated |
03 30 00.09 | Cast-In-Place Concrete - Short Form | Updated |
03 31 23.13 | High-Performance Structural Concrete for Bridge Decks | Editorial Changes |
03 35 00 | Concrete Finishing | Editorial Changes |
03 35 46 | Concrete Floor Hardening | Editorial Changes |
03 37 13 | Shotcrete | Updated |
03 37 26 | Underwater Placed Concrete | Editorial Changes |
03 41 00 | Precast Structural Concrete | Updated |
03 48 00 | Precast concrete specialties | Updated |
04 03 01.13 | Period masonry cleaning | Editorial Changes |
05 12 23 | Structural Steel for Buildings | Updated |
05 12 33 | Structural Steel for Bridges | Editorial Changes |
05 14 00 | Structural Aluminum for Buildings | Editorial Changes |
05 21 00 | Steel Joist Framing | Editorial Changes |
05 31 00 | Steel Decking | Editorial Changes |
05 41 00 | Structural Metal Stud Framing | Editorial Changes |
05 50 00 | Metal Fabrications | Editorial Changes |
05 51 00 | Metal Stairs and Ladders | Editorial Changes |
05 52 16 | Modular Workplace Guardrail System | Editorial Changes |
06 40 23.13 | Plastic Laminate Finishing for Interior Architectural Woodwork | Editorial Changes |
07 21 26.16
Formerly: 07 21 29.02 |
Blown Insulation - Mineral Fibre
Formerly: Sprayed Insulation - Mineral Fibre |
Renumbered, Renamed and updated |
07 53 23 | Ethylene-Propylene-Diene-Monomer Roofing | Editorial Changes |
07 84 00 | Fire Stopping | Updated |
08 50 00 | Windows | Updated |
09 64 29 | Wood Strip and Plank Flooring | Editorial Changes |
33 32 13.13 | Packaged Sewage Lift, Wet Well Type | Editorial Changes |
33 65 33 | Telethermics - Dryable Drainable, Testable Conduit Systems | Editorial Changes |
NMS summary of updates 2018-01
The 2018-01 NMS publication includes two new sections, on designated substances reporting, as well as epoxy injection and chemical grouting.
Technical content in Divisions 01, 02, 03, 08, 22, 23, 25 and 26 were updated, and editorial changes were made to other Sections listed.
Technical updates
Section | Title | Status |
---|---|---|
01 14 25 | Designated Substances Report | New |
01 51 00 | Temporary Utilities | Editorial ChangesFootnote** |
01 73 00 | Execution | UpdatedFootnote* |
02 83 10 | Lead - Base Paint Abatement - Minimum Precautions | UpdatedFootnote* |
02 83 11 | Lead - Base Paint Abatement - Intermediate Precautions | UpdatedFootnote* |
02 83 12 | Lead - Base Paint Abatement - Maximum Precautions | UpdatedFootnote* |
02 84 00 | Polychlorinate Biphenyl Remediation | UpdatedFootnote* |
03 01 36 | Epoxy Injection/Chemical Grout | New |
03 10 00 | Concrete Forming and Accessories | Editorial ChangesFootnote** |
03 11 19 | Insulating concrete forms | UpdatedFootnote* |
03 20 00 | Concrete Reinforcing | Editorial ChangesFootnote** |
07 03 30.13 | Conservation Treatment for Period Canvas Roofing | Editorial ChangesFootnote** |
07 03 30.16 | Conservation Treatment for Period Board Roofing | Editorial ChangesFootnote** |
08 44 13 | Glazed Aluminum Curtain Walls | UpdatedFootnote* |
08 44 23 | Structural Sealant Glazed Curtain Walls | UpdatedFootnote* |
22 05 05 | Selective Demolition for Plumbing | UpdatedFootnote* |
23 05 05 | Selective Demolition for Heating, Ventilating, and Air Conditioning (HVAC) | UpdatedFootnote* |
23 05 15 | Common Installation Requirements for HVAC Pipework | UpdatedFootnote* |
23 05 48 | Seismic Restraint Systems (SRS) - Type P2 Buildings | UpdatedFootnote* |
23 05 48.16 | Seismic Restraint Systems (SRS) - Type P2 Buildings | Editorial ChangesFootnote** |
23 11 26 | Facility Liquid-Petroleum Gas Piping | Editorial ChangesFootnote** |
23 22 13.13 | High Pressure Steam and Condensate Heating Piping Systems | UpdatedFootnote* |
23 31 13.01 | Metal Ducts - Low Pressure to 500 Pa | UpdatedFootnote* |
23 31 13.02 | Metal Ducts - High Pressure to 2500 Pa | UpdatedFootnote* |
23 33 16 | Dampers - Fire and Smoke | UpdatedFootnote* |
25 05 60 | Emcs: Field Installation | UpdatedFootnote* |
25 30 02 | Emcs: Field Control Devices | UpdatedFootnote* |
26 05 05 | Selective Demolition for Electrical | UpdatedFootnote* |
26 05 36 | Cable Trays for Electrical Systems | UpdatedFootnote* |
NMS summary of updates 2017-10
The 2017–10 NMS publication includes updates to technical content in Divisions 21, 22, 23, 33 and 42. Extensive editorial changes were made to all sections listed as well as renumbering and renaming a large number of sections in alignment with MasterFormat® 2016.
Technical updates
Section | Title | Status |
---|---|---|
01 12 00 | Multiple Contract Summary | Updated |
01 33 29
Formerly: 01 47 17 |
Sustainable Design Reporting
Formerly: Sustainable Requirements: Contractor's Verification |
Renumbered and Renamed |
01 74 00 | Cleaning | Editorial Changes |
01 91 13.16 | Commissioning Forms | Editorial Changes |
02 56 13 | Waste Containment | Editorial Changes |
06 41 93
Formerly: 08 70 05 |
Cabinet and Miscellaneous Hardware
Formerly: Cabinet and Miscellaneous Hardware |
Renumbered |
08 03 52 | Conservation Treatment for Period Wood Windows | Editorial Changes |
08 36 13.13
Formerly: 08 36 13.01 |
Sectional Wood Doors
Formerly: Sectional Wood Doors |
Renumbered |
08 36 13.16
Formerly: 08 36 13.02 |
Sectional Metal Doors
Formerly: Sectional Metal Doors |
Renumbered |
08 36 13.19
Formerly: 08 36 13.03 |
Sectional Plastic Doors
Formerly: Sectional Plastic Doors |
Renumbered |
08 36 19.13
Formerly: 08 36 19.01 |
Multi-Leaf Vertical Lift Wood Doors
Formerly: Vertical Lift Wood Doors |
Renumbered and Renamed |
08 36 19.16
Formerly: 08 36 19.02 |
Multi-Leaf Vertical Lift Metal Doors
Formerly: Multi-Leaf Vertical Lift Metal Doors |
Renumbered |
08 44 23
Formerly: 08 44 26.13 |
Structural Sealant Glazed Curtain Walls
Formerly: Structural Sealant Glazed Assemblies |
Renumbered and Renamed |
08 62 00
Formerly: 08 62 10 |
Plastic Skylights
Formerly: Plastic Skylights |
Renumbered |
08 80 00
Formerly: 08 80 50 |
Glazing
Formerly: Glazing |
Renumbered |
08 87 23.16
Formerly: 08 87 53 |
Security Films
Formerly: Security Films |
Renumbered |
09 01 90.62
Formerly: 09 91 13.01 |
Exterior Repainting
Formerly: Exterior Re-Painting |
Renumbered and Renamed |
09 01 90.63
Formerly: 09 91 23.01 |
Interior Re-Painting
Formerly: Interior Re-Painting |
Renumbered |
09 03 25
Formerly: 09 03 51 |
Conservation Treatment for Period Plastering
Formerly: Historic - Plaster |
Renumbered and Renamed |
09 03 91.13
Formerly: 09 03 61 |
Conservation Treatment for Period Exterior Painting
Formerly: Historic - Repainting Exterior Surfaces |
Renumbered and Renamed |
09 03 91.23
Formerly: 09 03 62 |
Conservation Treatment for Period Interior Painting
Formerly: Historic - Repainting Interior Surfaces |
Renumbered and Renamed |
09 21 16.08
Formerly: 09 21 99 |
Gypsum Board Assemblies for Minor Works
Formerly: Partitions for Minor Works |
Renumbered and Renamed |
09 22 00
Formerly: 09 22 14 |
Supports for Plaster and Gypsum Board
Formerly: Furring and Lathing |
Renumbered and Renamed |
09 51 99 | Acoustical Ceilings for Minor Works | Deleted |
09 53 00.01 | Acoustical Suspension | Deleted |
09 65 00.08
Formerly: 09 65 99 |
Resilient Flooring for Minor Works
Formerly: Resilient Flooring for Minor Works |
Renumbered |
09 66 16 | Terrazzo Floor Tile
Formerly: Terrazzo Floor Tiling |
Renamed |
09 91 00.08
Formerly: 09 91 99 |
Painting for Minor Works
Formerly: Painting for Minor Works |
Renumbered |
10 22 19.54
Formerly: 10 22 19 |
Demountable Partitions - Post and Panel
Formerly: Post and Panel Demountable Partitions |
Renumbered and Renamed |
10 22 19.55
Formerly: 10 22 19.01 |
Demountable Partitions - Stud Type
Formerly: Stud Type Demountable Partitions |
Renumbered and Renamed |
10 22 33
Formerly: 10 22 26.13 |
Accordion Folding Partitions
Formerly: Accordion Folding Partitions |
Renumbered |
10 22 39
Formerly: 10 22 26.33 |
Folding Panel Partitions
Formerly: Folding Panel Partitions |
Renumbered |
10 26 00
Formerly: 10 26 00.01 |
Wall and Door Protection
Formerly: Wall and Corner Guards |
Renumbered and Renamed |
10 28 00
Formerly: 10 28 10 |
Toilet and Bath Accessories
Formerly: Toilet and Bath Accessories |
Renumbered |
10 44 00
Formerly: 10 44 16.19 |
Fire Protection Specialties
Formerly: Fire Extinguishers and Safety Blankets |
Renumbered and Renamed |
11 11 00
Formerly: 23 10 01 |
Vehicle Service Equipment
Formerly: Service Garage Systems |
Renumbered and Renamed |
11 13 19.23
Formerly: 11 13 30 |
Loading Dock Lifts
Formerly: Elevating Docks |
Renumberedand Renamed |
11 41 23
Formerly: 11 41 10 |
Walk-In Coolers and Freezers
Formerly: Walk-In Freezers and Coolers |
Renumbered and Renamed |
11 53 13
Formerly: 23 38 16.13 |
Laboratory Fume Hoods
Formerly: Fume Hoods [for Laboratories] |
Renumbered and Renamed |
11 81 19
Formerly: 11 24 19 |
Vacuum Cleaning Systems
Formerly: Vacuum Cleaning Systems |
Renumbered |
11 82 26 | Facility Waste Compactors
Formerly: Waste Compactors and Destructors |
Renamed |
12 35 39
Formerly: 11 40 20 |
Commercial Kitchen Casework
Formerly: Food Service Custom Equipment |
Renumbered, Renamed and updated |
12 35 53.13 | Metal Laboratory Casework
Formerly: Steel Laboratory Casework |
Renamed |
13 34 23 | Prefabricated Structures
Formerly: Prefabricated Buildings |
Renamed |
21 05 01 | Common Work Results for Mechanical | Deleted |
21 05 00
Formerly: 21 05 05 |
Common Work Results for Fire Suppression
Formerly: Common Work Results for Fire Suppression |
Renumbered and Updated |
21 12 00
Formerly: 21 12 01 |
Fire-Suppression Standpipes and Hose Assemblies
Formerly: Standpipe and Hose Assembly |
Renumbered and Renamed |
21 21 16.13
Formerly: 21 21 00.01 |
Carbon Dioxide Fire Extinguishing Equipment: Total Flooding
Formerly: Carbon Dioxide Extinguishing Systems - Total Flooding |
Renumbered and Renamed |
21 21 16.16
Formerly: 21 21 00.02 |
Carbon Dioxide Fire Extinguishing Systems: Local Application
Formerly: Carbon Dioxide Extinguishing Systems - Local Application |
Renumbered and Renamed |
22 05 00 | Common Work Results for Plumbing | Updated |
22 05 15
Formerly: 22 42 01 |
Plumbing Specialties and Accessories
Formerly: Plumbing Specialties and Accessories |
Renumbered |
22 11 16 | Domestic Water Piping | Updated |
22 13 16.13
Formerly: 22 13 17 |
Sanitary Waste and Vent Piping - Cast Iron and Copper
Formerly: Drainage Waste and Vent Piping - Cast Iron and Copper |
Renumbered and Renamed |
22 13 16.16
Formerly: 22 13 18 |
Sanitary Waste and Vent Piping - Plastic
Formerly: Drainage Waste and Vent Piping - Plastic |
Renumbered and Renamed |
22 15 00 | General Service Compressed-Air Systems | Updated |
22 31 16 | Commercial Domestic Water Softeners
Formerly: Commercial Domestic Water Softening |
Renamed |
22 33 00
Formerly: 22 30 05 |
Electrical Domestic Water Heaters
Formerly: Domestic Water Heaters |
Renumbered and Renamed |
22 42 13
Formerly: 22 42 03 |
Commercial Water Closets, Urinals, and Bidets
Formerly: Commercial Washroom Fixtures |
Renumbered and Renamed |
22 42 19
Formerly: 22 42 20 |
Commercial Bathtubs and Showers
Formerly: Commercial Showers and Bathtubs |
Renumbered and Renamed |
23 01 05
Formerly: 23 05 01 |
Operation and Maintenance of HVAC Systems During Construction
Formerly: Use of HVAC Systems During Construction |
Renumbered and Renamed |
23 01 31 | Air Duct Cleaning for HVAC Systems | Editorial Changes |
23 05 00 | Common Work Results for HVAC | Updated |
23 05 05 | Selective Demolition for Heating, Ventilating, and Air Conditioning (HVAC) | Editorial Changes |
23 05 15 | Common Installation Requirements for HVAC Pipework | Editorial Changes |
23 05 16 | Expansion Fittings and Loops for HVAC Piping | Editorial Changes |
23 05 17 | Pipe Welding | Editorial Changes |
23 05 19 | Meters and Gauges for HVAC Piping | Editorial Changes |
23 05 19.13
Formerly: 23 05 19.01 |
Thermometers and Pressure Gauges - Piping Systems
Formerly: Thermometers and Pressure Gauges - Piping Systems |
Renumbered |
23 05 23.01 | Valves - Bronze | Editorial Changes |
23 05 23.02 | Valves - Cast Iron | Editorial Changes |
23 05 23.03 | Valves - Cast Steel | Editorial Changes |
23 05 23.04 | Valves - Lubricated Plug | Editorial Changes |
23 05 23.05 | Butterfly Valves | Editorial Changes |
23 05 29 | Hangers and Supports for HVAC Piping and Equipment | Editorial Changes |
23 05 33 | Heat Tracing for HVAC Piping
Formerly: Heat Tracing for HVAC Piping and Tanks |
Renamed |
23 05 48 | Vibration and Seismic Controls for HVAC
Formerly: Vibration and Seismic Controls for HVAC Piping and Equipment |
Renamed |
23 05 48.16
Formerly: 23 05 49.01 |
Seismic Restraint Systems (SRS) - Type P2 Buildings
Formerly: Seismic Restraint Systems (SRS) - Type P2 Buildings |
Renumbered |
23 05 53
Formerly: 23 05 53.01 |
Identification for HVAC Piping and Equipment
Formerly: Mechanical Identification |
Renumbered and Renamed |
23 05 93 | Testing, Adjusting, and Balancing for HVAC | Editorial Changes |
23 05 93.13 | Testing, Adjusting and Balancing of Fume Hoods | Editorial Changes |
23 05 94 | Pressure Testing of Ducted Air Systems | Editorial Changes |
23 07 13 | Duct Insulation | Editorial Changes |
23 07 16
Formerly: 23 07 14 |
HVAC Equipment Insulation
Formerly: Thermal Insulation for Equipment |
Renumbered and Renamed |
23 07 19
Formerly: 23 07 15 |
HVAC Piping Insulation
Formerly: Thermal Insulation for Piping |
Renumbered and Renamed |
23 08 13
Formerly: 23 08 01 |
Performance Verification HVAC Systems
Formerly: Performance Verification Mechanical Piping Systems |
Renumbered and Renamed |
23 08 16
Formerly: 23 08 02 |
Cleaning and Start-Up of HVAC Piping Systems
Formerly: Cleaning and Start-Up of Mechanical Piping Systems |
Renumbered and Renamed |
23 09 33 | Electric and Electronic Control System for HVAC | Editorial Changes |
23 09 43 | Pneumatic Control System for HVAC | Editorial Changes |
23 11 13 | Facility Fuel-Oil Piping | Editorial Changes |
23 11 23 | Facility Natural Gas Piping | Editorial Changes |
23 11 26 | Facility Liquefied-Petroleum Gas Piping
Formerly: Facility Liquid-Petroleum Gas Piping |
Renamed and updated |
23 21 13.01 | Hydronic Systems: Copper | Updated |
23 21 13.02 | Hydronic Systems: Steel | Updated |
23 21 13.03 | Press Joint Piping Systems Hydronic Systems | Updated |
23 21 16
Formerly: 23 21 14 |
Hydronic Piping Specialties
Formerly: Hydronic Specialties |
Renumbered and Renamed |
23 21 23 | Hydronic Pumps | Editorial Changes |
23 22 13 | Steam and Condensate Heating Piping | Updated |
23 22 13.13
Formerly: 23 20 13 |
High Pressure Steam and Condensate Heating Piping Systems
Formerly: High Pressure Piping Systems Inside Buildings and CHC Plants |
Renumbered, Renamed and updated |
23 22 16
Formerly: 23 22 14 |
Steam and Condensate Heating Piping Specialties
Formerly: Steam Specialties |
Renumbered and Renamed |
23 22 23 | Steam Condensate Pumps | Editorial Changes |
23 23 00 | Refrigerant Piping | Editorial Changes |
23 25 00 | HVAC Water Treatment
Formerly: HVAC Water Treatment Systems |
Renamed and updated |
23 31 13.01 | Metal Ducts - Low Pressure to 500 Pa | Editorial Changes |
23 31 13.02 | Metal Ducts - High Pressure to 2500 Pa | Editorial Changes |
23 32 48 | Acoustical Air Plenums | Editorial Changes |
23 33 00 | Air Duct Accessories | Editorial Changes |
23 33 14 | Dampers – Balancing | Editorial Changes |
23 33 15 | Dampers – Operating | Editorial Changes |
23 33 16 | Dampers - Fire and Smoke | Editorial Changes |
23 33 46 | Flexible Ducts | Editorial Changes |
23 33 53 | Duct Liners | Editorial Changes |
23 34 00 | HVAC Fans | Editorial Changes |
23 34 00.13
Formerly: 23 34 24 |
Domestic Fans
Formerly: Domestic Fans |
Renumbered |
23 34 23.13
Formerly: 23 34 25 |
Packaged Roof and Wall Exhausters
Formerly: Packaged Roof and Wall Exhausters |
Renumbered |
23 35 16 | Engine Exhaust Systems | Editorial Changes |
23 36 00 | Air Terminal Units | Editorial Changes |
23 37 13 | Diffusers, Registers and Grilles | Editorial Changes |
23 37 20 | Louvres, Intakes and Vents | Editorial Changes |
23 38 13 | Commercial Kitchen Hoods | Editorial Changes |
23 38 17 | Perchloric Acid Fume Hood and Exhaust System - Stainless Steel | Editorial Changes |
23 38 18 | Perchloric Acid Fume Hood and Exhaust System - Plastic | Editorial Changes |
23 40 00
Formerly: 23 44 00 |
HVAC Air Cleaning Devices
Formerly: HVAC Air Filtration |
Renumbered and Renamed |
23 51 00 | Breechings, Chimneys and Stacks | Editorial Changes |
23 52 00 | Heating Boilers | Editorial Changes |
23 54 13 | Electric-Resistance Furnaces | Editorial Changes |
23 54 16 | Fuel-Fired Furnaces | Editorial Changes |
23 55 13
Formerly: 23 55 01 |
Fuel-Fired Duct Heaters
Formerly: Duct Heaters |
Renumbered and Renamed |
23 56 13.13
Formerly: 23 56 13.01 |
Heating Solar Flat- Plate Collectors
Formerly: Heating Solar Flat Plate Collectors |
Renumbered and Renamed |
23 57 00 | Heat Exchangers for HVAC | Editorial Changes |
23 64 13 | Absorption Water Chillers | Editorial Changes |
23 64 16 | Centrifugal Water Chillers | Editorial Changes |
23 64 19 | Reciprocating Water Chillers | Editorial Changes |
23 64 26 | Rotary-Screw Water Chillers | Editorial Changes |
23 65 10 | Condensers, Coolers and Cooling Towers | Editorial Changes |
23 65 16 | Natural- Draft Cooling Towers | Editorial Changes |
23 72 00 | Air-to-Air Energy Recovery Equipment | Editorial Changes |
23 73 00.13
Formerly: 23 73 10 |
Air Handling - Built-Up
Formerly: Air Handling - Built-Up |
Renumbered |
23 73 00.16
Formerly: 23 73 11 |
Air Handling Units – Packaged
Formerly: Air Handling Units – Packaged |
Renumbered |
23 74 00 | Packaged Outdoor HVAC Equipment | Editorial Changes |
23 81 23 | Computer Room Air Conditioning | Editorial Changes |
23 81 40 | Air and Water Source Unitary Heat Pumps | Editorial Changes |
23 82 00.13
Formerly: 23 82 20 |
Forced Air Heaters
Formerly: Forced Air Heaters |
Renumbered |
23 82 00.16
Formerly: 23 82 21 |
Incremental Heating and Cooling Units
Formerly: Incremental Heating and Cooling Units |
Renumbered |
23 81 40 | Air and Water Source Unitary Heat Pumps | Editorial Changes |
23 81 40 | Air and Water Source Unitary Heat Pumps | Editorial Changes |
23 82 00.13
Formerly: 23 82 20 |
Forced Air Heaters
Formerly: Forced Air Heaters |
Renumbered |
23 82 00.16
Formerly: 23 82 21 |
Incremental Heating and Cooling Units
Formerly: Incremental Heating and Cooling Units |
Renumbered |
23 82 19 | Fan Coil Units | Editorial Changes |
23 82 23 | Unit Ventilators | Editorial Changes |
23 82 33.13
Formerly: 23 82 33.01 |
Residential Convectors
Formerly: Residential Convectors |
Renumbered |
23 82 33.16
Formerly: 23 82 33.02 |
Commercial Convectors
Formerly: Commercial Convectors |
Renumbered |
23 82 33.19
Formerly: 23 82 33.03 |
Cabinet Convector Heaters
Formerly: Cabinet Convector Heaters |
Renumbered |
23 82 36 | Finned Tube Radiation Heaters | Editorial Changes |
23 82 39 | Unit Heaters | Editorial Changes |
23 82 39.23
Formerly: 23 82 39.01 |
Unit Heaters – Electric
Formerly: Unit Heaters – Electric |
Renumbered |
23 82 39.26
Formerly: 23 82 39.02 |
Liquid Heaters
Formerly: Liquid Heaters |
Renumbered |
23 83 00 | Radiant Heating Units | Editorial Changes |
23 83 00.13
Formerly: 23 83 00.01 |
Radiant Heaters - Electric Infrared
Formerly: Radiant Heaters - Electric Infrared |
Renumbered |
23 83 13 | Radiant Heating Electric Cables | Editorial Changes |
23 83 13.19
Formerly: 23 83 13.01 |
Radiant Heating Electric Cables - Snow Melting
Formerly: Radiant Heating Electric Cables - Snow Melting |
Renumbered |
23 83 13.23
Formerly: 23 83 13.02 |
Radiant Heating Electric Cables - Floor Warming
Formerly: Radiant Heating Electric Cables - Floor Warming |
Renumbered |
23 84 13 | Humidifiers | Editorial Changes |
26 13 16
Formerly: 26 13 17 |
Medium-Voltage Fusible Interrupter Switchgear
Formerly: Full Load Interrupter Switches to 15 kV |
Renumbered and Renamed |
26 33 53 | Static Uninterruptible Power Supply
Formerly: Uninterruptible Power Systems Static (Ups) |
Renamed |
26 52 13.13
Formerly: 26 52 00 |
Emergency Lighting
Formerly: Emergency Lighting |
Renumbered |
26 53 13
Formerly: 10 14 43 |
Photoluminescent Signage
Formerly: Photoluminescent (PLM) Exit Signs |
Renumbered and Renamed |
28 10 00
Formerly: 28 13 00 |
Access Control
Formerly: Access Control |
Renumbered |
28 14 00
Formerly: 28 13 19 |
Access Control System Hardware
Formerly: Access Control Systems Infrastructure |
Renumbered and Renamed |
28 31 00
Formerly: 28 16 00 |
Intrusion Detection
Formerly: Intrusion Detection |
Renumbered and Updated |
28 46 00
Formerly: 28 31 00 |
Fire Detection and Alarm
Formerly: Fire Detection and Alarm |
Renumbered |
31 05 16 | Aggregates for Earthwork
Formerly: Aggregate Materials |
Renamed |
31 08 13
Formerly: 31 09 16.28 |
Pile Load Testing
Formerly: Pile Tests |
Renumbered and Renamed |
31 53 13
Formerly: 31 53 13.01 |
Timber Cribwork
Formerly: Timber Cribwork |
Renumbered |
31 62 16.13 | Sheet Steel Piles
Formerly: Steel Sheet Piles |
Renamed |
32 01 90.23
Formerly: 32 93 43.01 |
Pruning
Formerly: Tree Pruning |
Renumbered and Renamed |
32 12 19.13
Formerly: 32 12 16.16 |
Road-Mix Asphalt paving Wearing Courses
Formerly: Road-Mix Asphalt paving Wearing Courses |
Renumbered |
32 13 13.17 | Roller Compacted Concrete Paving
Formerly: Roller Compacted Concrete Pavements |
Renamed |
33 05 14.03 | Telethermics Pre-Fabricated Steel Maintenance Holes | Updated |
33 11 00
Formerly: 33 21 00 |
Groundwater Sources
Formerly: Water Supply Wells |
Renumbered and Renamed |
33 14 16
Formerly: 33 11 16 |
Site Water Utility Distribution Piping
Formerly: Site Water Utility Distribution Piping |
Renumbered |
33 14 16.13
Formerly: 33 11 16.01 |
Incoming Site Water Utility Distribution Piping
Formerly: Incoming Site Water Utility Distribution Piping |
Renumbered |
33 31 11
Formerly: 33 31 13 |
Public Sanitary Sewerage Gravity Piping
Formerly: Public Sanitary Utility Sewerage Piping |
Renumbered and Renamed |
33 31 23
Formerly: 33 34 00 |
Sanitary Sewerage Force Mains Piping
Formerly: Sanitary Utility Sewerage Force Mains |
Renumbered and Renamed |
33 41 16
Formerly: 33 46 16 |
Subdrainage Piping
Formerly: Subdrainage Piping |
Renumbered |
33 56 13 | Aboveground Fuel -Storage Tanks | Editorial Changes |
33 56 16 | Underground Fuel- Storage Tanks | Editorial Changes |
33 65 13 | Telethermics - Distribution Piping – Steel | Updated |
33 65 33 | Telethermics - Dryable Drainable, Testable Conduit Systems | Updated |
33 65 43 | Telethermics - Steel Tunnel Systems | Updated |
33 65 46 | Telethermics - Shallow Inverted Trench (SIT) Systems | Updated |
34 77 13 | Passenger Boarding Bridges
Formerly: Passenger Loading Bridges |
Renamed |
42 20 00 | Process Cooling Equipment | Updated |
NMS summary of updates 2017-07
The 2017–07 NMS update releases adjustments for 41 NMS Sections as follows:
- Updating 34 Sections to incorporate comments received from a range of stakeholders including Public Services and Procurement Canada, and the Department of National Defence
- Adding two new NMS sections to Division 02 to specify selective demolition only for exterior and interior building elements, considering sustainability requirements
- Renumbering and changing Titles of 19 NMS Sections to align with MasterFormat® 2016
Technical updates
Section | Title | Status |
---|---|---|
00 11 19.53
Formerly: 00 11 21 |
Request for Proposal - Design Build (Single Prime Contract)
Formerly: Request for Proposal - Design-Build |
Renamed and Renumbered |
01 32 16.19
Formerly: 01 32 16.07 |
Construction Progress Schedule - Bar (Gantt) Chart
Formerly: Construction Progress Schedule - Bar (Gantt) Chart |
Renumbered and Updated |
01 35 29.13
Formerly: 01 35 29.14 |
Health, Safety, and Emergency Response Procedures for Contaminated Sites
Formerly: Health and Safety for Contaminated Sites |
Renumbered, Renamed and updated |
01 35 35 | DND Fire Safety Requirements | Updated |
01 47 17 | Sustainable Requirements: Contractor's Verification | Updated |
01 74 00
Formerly: 01 74 11 |
Cleaning
Formerly: Cleaning |
Renumbered and Updated |
01 74 19.13
Formerly: 01 35 43.10 |
Carpet Reclamation
Formerly: Carpet Reclamation |
Renumbered |
01 79 00.13
Formerly: 01 91 41 |
Demonstration and Training for Building Commissioning
Formerly: Commissioning: Training |
Renumbered and Renamed |
01 91 13.13
Formerly: 01 91 31 |
Commissioning Plan
Formerly: Commissioning (CX) Plan |
Renumbered, Renamed and updated |
01 91 13.16
Formerly: 01 91 33 |
Commissioning Forms
Formerly: Commissioning Forms |
Renumbered, Renamed and updated |
01 92 00
Formerly: 01 91 51 |
Facility Operation
Formerly: Building Management Manual (BMM) |
Renumbered, Renamed and updated |
02 03 44 | Shoring and Support of Period Structures
Formerly: Shoring and Support of Historic Structures |
Renamed |
02 25 29.23
Formerly: 02 27 16 |
Roofing Investigations - Thermographic
Formerly: Thermographic Assessment - Roof |
Renumbered, Renamed and updated |
02 41 13 | Selective Site Demolition | Updated |
02 41 16 | Structure demolition | Updated |
02 41 19.13 | Selective Building Demolition | New |
02 41 19.16 | Selective Interior Demolition | New |
02 50 00
Formerly: 02 61 00.01 |
Site Remediation
Formerly: Soil Remediation |
Renumbered, Renamed and updated |
02 56 13
Formerly: 02 50 13 |
Waste Containment
Formerly: Management of Toxic Waste |
Renumbered, Renamed and updated |
02 87 13.13
Formerly: 02 85 00.01 |
Precautions for Mould Remediation - Minimum Precautions
Formerly: Mould Remediation - Minimum Precautions |
Renumbered, Renamed and updated |
02 87 13.14
Formerly: 02 85 00.02 |
Precautions for Mould Remediation - Medium Precautions
Formerly: Mould Remediation - Medium Precautions |
Renumbered, Renamed and updated |
02 87 13.15
Formerly: 02 85 00.03 |
Precautions for Mould Remediation - Maximum Precautions
Formerly: Mould Remediation - Maximum Precautions |
Renumbered, Renamed and updated |
03 10 00 | Concrete Forming and Accessories | Updated |
03 11 19 | Insulating Concrete Forming
Formerly: Insulated Concrete Forms |
Updated and Renamed |
03 30 00 | Cast-In-Place Concrete | Updated |
03 30 00.09 | Cast-In-Place Concrete Short Form | Updated |
03 31 23.13 | High Performance Structural Concrete for Bridge Decks | Updated |
03 41 00 | Precast Structural Concrete | Updated |
04 01 20.93 | Testing and Sampling Brick Units for Restoration | Updated |
04 03 01.13 | Period masonry cleaning | Updated |
04 03 05.13 | Period masonry mortaring | Updated |
04 03 05.16 | Period masonry grouting | Updated |
04 03 05.21 | Period masonry repointing | Updated |
04 03 43.13 | Period stone Repairing | Updated |
04 03 43.16 | Period stone Replacing | Updated |
04 03 43.19 | Period stone Dismantling | Updated |
04 20 00.08 | Masonry for Minor Works | Updated |
04 71 13.13
Formerly: 04 71 14 |
Prefaced Calcium Silicate Manufactured Brick Masonry
Formerly: Calcium Silicate Manufactured Unit Masonry |
Renumbered, Renamed and updated |
09 68 13 | Tile Carpeting | Updated |
34 43 05.39 | Airfield Approach Light Support Structures | Updated |
34 43 26.19 | Airfield Lighting Regulator Assembly | Updated |
NMS summary of updates 2017-04
The 2017–04 NMS update features updates to several material categories such as concrete and steel as well as updates to sections on transportation and disposal of hazardous materials and Regulatory requirements. In addition to updates on selective demolition, this publication introduces new sections related to selective demolition for electrical, plumbing and HVAC.
Technical updates
Section | Title | Status |
---|---|---|
01 32 16.16
Formerly: 01 32 16.06 |
Construction Progress Schedule - Critical Path Method (CPM)
Formerly: Construction Progress Schedule - Critical Path Method (CPM) |
Updated and Renumbered |
01 41 00 | Regulatory requirements | Updated |
01 74 19
Formerly: 01 74 21 |
waste management and disposal
Formerly: Construction/Demolition waste management and disposal |
Renumbered, Renamed and updated |
02 03 43 | Period Structure Relocating | Updated |
02 41 00.08
Formerly: 02 41 99 |
Demolition - Minor Works
Formerly: Demolition for Minor Works |
Renumbered, Renamed and updated |
02 41 13.13 | Paving Removal | Updated |
02 41 16.09
Formerly: 02 41 16.01 |
Structure demolition - Short Form
Formerly: Structure demolition - Short Form |
Renumbered and Updated |
02 42 00 | Removal and Salvage of Construction Materials | Updated |
02 42 13 | Deconstruction of Structures | Updated |
02 65 00 | Underground Storage Tank Removal | Updated |
02 81 00
Formerly: 02 81 01 |
Transportation and Disposal of Hazardous Materials
Formerly: Hazardous Materials |
Renumbered, Renamed and updated |
03 20 00 | Concrete Reinforcing | Updated |
03 35 00 | Concrete Finishing | Updated |
03 35 46
Formerly: 03 35 05 |
Concrete Topical Treatments
Formerly: Concrete Floor Hardening |
Renumbered, Renamed and updated |
03 41 36 | Precast Structural Post-Tensioned Concrete | Updated |
04 05 00 | Common Work Results for Masonry | Updated |
04 05 13
Formerly: 04 05 12 |
Masonry Mortaring and Grouting
Formerly: Masonry Mortar and Grout |
Renumbered, Renamed and updated |
04 05 19 | Masonry Anchorage and Reinforcing | Updated |
04 05 23 | Masonry Accessories | Updated |
05 14 00
Formerly: 05 14 11 |
Structural Aluminum Framing
Formerly: Structural Aluminum for Buildings |
Renumbered, Renamed and updated |
05 21 00 | Steel Joist Framing | Updated |
05 31 00 | Steel Decking | Updated |
05 41 00 | Structural Metal Stud Framing | Updated |
05 50 00 | Metal Fabrications | Updated |
05 51 00
Formerly: 05 51 29 |
Metal Stairs and Ladders
Formerly: Metal Stairs and Ladders |
Renumbered and Updated |
06 18 00 | Glued-Laminated Construction | Updated |
06 20 00 | Finish Carpentry | Updated |
06 40 00 | Architectural Woodwork | Updated |
07 46 16 | Aluminum Siding | Updated |
07 46 19 | Steel Siding | Updated |
07 46 23 | Wood Siding | Updated |
07 46 33 | Plastic Siding | Updated |
08 11 16 | Aluminum Doors and Frames | Updated |
08 11 19 | Stainless-Steel Doors and Frames | Updated |
08 50 00 | Windows | Updated |
09 21 16 | Gypsum Board Assemblies | Updated |
09 22 16 | Non-Structural Metal Framing | Updated |
09 68 13 | Tile Carpeting | Updated |
22 05 05 | Selective Demolition for Plumbing | New |
23 05 05 | Selective Demolition for Heating, Ventilating, and Air Conditioning (HVAC) | New |
23 05 15
Formerly: 23 05 05 |
Common Installation Requirements for HVAC Pipework
Formerly: Installation of Pipework |
Renumbered and Renamed |
26 05 05 | Selective Demolition for Electrical | New |
26 52 13.16
Formerly: 26 53 00 |
Exit Signs
Formerly: Exit Signs |
Renumbered and Updated |
32 16 00
Formerly: 32 16 15 |
Curbs, Gutters and Sidewalks
Formerly: Concrete Walks, Curbs and Gutters |
Renumbered, Renamed and updated |
32 17 23 | Pavement Markings | Updated |
NMS summary of updates 2017-01
The 2017–01 NMS includes a new section that focuses on removal and salvage of construction materials and forming a preliminary component to other selective demolition activities. It also covers updated sections related to deconstruction of structures, removal of construction materials, removal of underground storage tanks, conservation treatment of period masonry and stone, as well as sections for cast-in-place concrete, wood treatment and rough carpentry. As a significant enhancement to the data set, descriptions are now provided for each NMS section. The descriptions will help users find appropriate sections, and will be searchable on the NRC's website, and within some of the third party software tools.
Technical updates
Section | Title | Status |
---|---|---|
01 41 00 | Regulatory requirements | Updated |
02 03 43 | Period Structure Relocating | Updated |
02 41 13.13
Formerly: 02 41 13.14 |
Paving Removal
Formerly: Asphalt paving Removal |
Updated, renamed and renumbered |
02 42 00 | Removal and Salvage of Construction Materials | New |
02 42 13 | Deconstruction of Structures | Updated |
02 65 00 | Underground Storage Tank Removal | Updated |
03 30 00 | Cast-In-Place Concrete | Updated |
03 30 00.09
Formerly: 03 30 00.01 |
Cast-In-Place Concrete - Short Form
Formerly: Cast-In-Place Concrete - Short Form |
Updated and renumbered |
03 31 23.13
Formerly: 03 30 51 |
High-Performance Structural Concrete for Bridge Decks
Formerly: Concrete for Bridge Decks |
Renumbered, Renamed and updated |
04 01 20.93
Formerly: 04 03 32 |
Testing and Sampling Brick Units for Restoration
Formerly: Historic - Testing and Sampling Brick Units |
Renumbered and Renamed and updated |
04 03 01.13
Formerly: 04 03 06 |
Period masonry cleaning
Formerly: Historic - Cleaning Masonry |
Renumbered and Renamed and updated |
04 03 05.13
Formerly: 04 03 08 |
Period masonry mortaring
Formerly: Historic - Mortaring |
Renumbered, Renamed and updated |
04 03 05.16
Formerly: 04 03 09 |
Period masonry grouting
Formerly: Historic - Grouting |
Renumbered, Renamed and updated |
04 03 05.21
Formerly: 04 03 07 |
Period masonry repointing
Formerly: Historic - Masonry Repointing |
Renumbered, Renamed and updated |
04 03 21.19
Formerly: 04 03 31 |
Clay Brick Conservation Treatment
Formerly: Historic - Repairing Brickwork |
Renumbered, Renamed and updated |
04 03 21.26 | Period Glazed Structural Clay Facing Tile Repair | New |
04 03 43.13
Formerly: 04 03 41 |
Period stone Repairing
Formerly: Historic - Repairing Stone |
Renumbered, Renamed and updated |
04 03 43.16
Formerly: 04 03 42 |
Period stone Replacing
Formerly: Historic - Replacing Stone |
Renumbered, Renamed and updated |
04 03 43.19
Formerly: 04 03 43 |
Period stone Dismantling
Formerly: Historic - Dismantling Stone Masonry |
Renumbered and renamed |
04 20 00.08
Formerly: 04 04 99 |
Masonry for Minor Works
Formerly: Masonry for Minor Works |
Renumbered and updated |
05 52 16
Formerly: 05 52 16 |
Modular Workplace Guardrail System
Formerly: Handrails at Roof Areas |
Updated and renamed |
06 05 73 | Wood Treatment | Updated |
06 10 00 | Rough Carpentry | Deleted |
06 10 53 | Miscellaneous rough carpentry | Updated |
06 40 23.13 | Plastic Laminate Finishing for Interior Architectural Woodwork | Updated |
07 42 13.23
Formerly: 07 42 43.01 |
Metal Composite Material Wall Panels
Formerly: Composite Metal Building Panels |
Renumbered and renamed |
07 42 46
Formerly: 07 44 56 |
Fibre Reinforced Cementitious Wall Panels
Formerly: Mineral Fiber Reinforced Cementitious Panels |
Renumbered, Renamed and updated |
07 56 13
Formerly: 07 55 56.14 |
Hot Fluid Applied Rubberized Asphalt Roofing
Formerly: Hot Fluid Applied Rubberized Asphalt Roofing |
Renumbered |
07 62 00 | Sheet Metal Flashing and Trim | Updated |
07 71 29
Formerly: 07 95 23 |
Manufactured Roof Expansion Joints
Formerly: Prefabricated Roof Expansion Joints |
Renumbered, Renamed and updated |
08 14 73
Formerly: 08 14 80 |
Sliding Wood and Plastic Doors
Formerly: Sliding Wood and Plastic Doors |
Renumbered |
08 31 00
Formerly: 08 31 00.01 |
Access Doors and Panels
Formerly: Access Doors - Mechanical |
Renumbered and renamed |
08 33 00
Formerly: 08 33 23.01 |
Overhead Coiling Doors and Grilles
Formerly: Overhead Coiling Doors and Grilles |
Renumbered |
08 34 59.13
Formerly: 08 34 58.01 |
Vault Doors and Frames
Formerly: Vault Doors and Frames |
Renumbered |
08 35 13.33
Formerly: 08 35 13.01 |
Panel Folding Doors
Formerly: Panel Folding Doors |
Renumbered |
08 42 26.33
Formerly: 08 34 83 |
Swinging All Glass Entrances
Formerly: Hinged Safety Glass Doors |
Renumbered and renamed |
09 51 13 | Acoustical Panel Ceilings | Updated |
11 81 29
Formerly: 07 72 69 |
Facility Fall Protection
Formerly: Roof Anchors and Safety Restraints |
Renumbered and renamed |
NMS summary of updates 2016-10
The 2016–10 NMS Update focuses on changes to sections related to conservation treatment of period construction, with four new sections on topics such as copper sheet roofing and period doors and windows. The domestic water piping Section was expanded to include Crosslinked Polyethylene (PEX) tubing. The Section on wastewater utility storage tanks now includes fibreglass reinforced polyester polyethylene and polyvinyl chloride in addition to precast concrete septic tanks.
Technical updates
Section | Title | Status |
---|---|---|
06 03 01.31
Formerly: 06 03 16 |
Period wood storage and protection
Formerly: Historic - Storage and protection of wood |
Renamed and renumbered |
06 03 05.73
Formerly: 06 03 74 |
Long-term period wood treatment
Formerly: Historic - Long-term treatment of wood |
Renamed and renumbered |
06 03 05.74
Formerly: 06 03 75 |
Eradication of insects in period wood
Formerly: Historic - Eradication of insects in wood |
Renamed and renumbered |
06 03 05.75
Formerly: 06 03 76 |
Antiseptic treatment of period wood
Formerly: Historic - Antiseptic treatment for wood |
Renamed and renumbered |
06 03 13
Formerly: 06 03 12 |
Conservation treatment of period log construction
Formerly: Historic - Period horizontal log work |
Renamed and renumbered |
06 03 13.23
Formerly: 06 03 15 |
Conservation treatment of period heavy timber
Formerly: Historic - Splicing of wood components |
Renamed and renumbered |
06 03 50.13
Formerly: 06 03 13 |
Carvel planking
Formerly: Historic - Carvel planking |
Renamed and renumbered |
06 03 50.16
Formerly: 06 03 18 |
Steam bending and replacement of curved wood members
Formerly: Historic - Replacement of curved wood members: Steam bending |
Renamed and renumbered |
06 03 50.19
Formerly: 07 03 90 |
Caulking period vessels
Formerly: Historic - Caulking period vessels |
Updated and renumbered |
06 10 53
Formerly: 06 10 00.01 |
Miscellaneous rough carpentry
Formerly: Rough carpentry - Short form |
Renamed and renumbered |
06 47 00
Formerly: 06 10 00.01 |
Plastic laminate finishing for interior architectural woodwork
Formerly: Plastic laminate finishing |
Renamed and renumbered |
07 03 30.13
Formerly: 07 03 34 |
Conservation treatment for period canvas roofing
Formerly: Historic - Canvas roofing |
Updated and renumbered |
07 03 30.16
Formerly: 07 03 36 |
Conservation treatment for period board roofing
Formerly: Historic - Board roofing |
Updated and renumbered |
07 03 31.26
Formerly: 07 03 13 |
Conservation treatment for period slate shingles
Formerly: Historic - Slate shingle roofing |
Renumbered and renamed |
07 03 31.29
Formerly: 07 03 32 |
Conservation treatment for period wood shingles and shakes
Formerly: Historic - Wood shingles and shakes roofing |
Updated, renamed and renumbered |
07 03 32.16
Formerly: 07 03 31 |
Conservation treatment for period concrete roof tiles
Formerly: Historic - Concrete unit roofing |
Renamed and renumbered |
07 03 33.13
Formerly: 07 03 33 |
Conservation treatment for period sod roofing
Formerly: Historic - Sod roofing |
Updated and renumbered |
07 03 41.13
Formerly: 07 03 35 |
Conservation treatment for period metal roof panels
Formerly: Historic - Tin-plate and terne plate roofing |
Renumbered and renamed |
07 03 61.21
Formerly: 07 03 61 |
Period copper sheet roof repair
Formerly: Historic - Copper sheet roof repair |
New, renumbered and renamed |
07 03 61.24
Formerly: 07 03 62 |
Period copper sheet roof replacing
Formerly: Historic - Period copper sheet roof replacing |
New, renumbered and renamed |
08 03 14.33 | Conservation treatment for period stile and rail wood doors
Formerly: Historic - Period stile and rail wood doors |
Updated and renamed |
08 03 51.23 | Conservation treatment for period steel windows
Formerly: Historic - Period hot-rolled steel casement window repairing |
New and renamed |
08 03 52 | Conservation treatment for period wood windows
Formerly: Historic - Period wood windows repairing |
New and renamed |
22 11 16 | Domestic water piping | Updated |
33 36 00 | Wastewater utility storage tanks
Formerly: Historic - Utility septic tanks |
Updated and renamed |
NMS summary of updates 2016-07
The 2016–07 NMS Update focuses on changes to sections in Divisions 26 and 34. Revisions were based on Aerodrome Standards and Recommended Practices TP 312 5th edition. New airfield lighting systems and LED lighting systems were introduced and the obstruction light Sections were updated.
Input for these updates was received from a range of stakeholders including manufacturers, the Canadian Airport Electrical Association, Public Services and Procurement Canada, Transport Canada and the Department of National Defence.
Technical updates
Section | Title | Status |
---|---|---|
01 35 13.13 | Special project procedures for airport facilities
Formerly: Special procedures for airport facilities |
Renamed |
01 50 13
Formerly: 01 52 01 |
Temporary facilities and controls for dredging
Formerly: Temporary facilities dredging |
Renamed and renumbered |
01 55 26
Formerly: 01 35 00.06 |
Traffic control
Formerly: Special procedures for traffic control |
Renamed and renumbered |
02 03 44
Formerly: 31 04 31 |
Shoring and support of historic structures
Formerly: Historic - Subgrade shoring and bracing |
Updated, renamed and renumbered |
06 40 00 | Architectural woodwork | Updated |
07 46 16 | Aluminum siding | New Sections created by splitting original content |
07 46 19
Formerly: 07 46 13 |
Steel siding
Formerly: Preformed metal siding |
|
09 91 23 | Interior painting | Updated |
26 12 16.13 | Pad-mounted, dry-type transformers for airfield visual aids
Formerly: Pad-mounted, transformers for airfield visual aids |
Updated, renamed |
26 29 02 | Fire pump control | Part 3 content restored |
26 55 36.13 | Medium-intensity red flashing obstruction lighting
Formerly: Medium-intensity (m.I.) red flashing obstruction light |
Updated |
26 55 36.16 | Medium-intensity white flashing obstruction lighting
Formerly: Medium-intensity (m.I.) white flashing obstruction light |
Updated and renamed |
26 55 36.19 | Low-intensity red flashing obstruction lighting
Formerly: Low-intensity (l.L.) red obstruction lighting |
Updated and renamed |
32 93 23.13
Formerly: 12 92 16 |
Interior plantings
Formerly: Interior plantings |
Updated and renumbered |
34 43 05 | Common work results for airfield lighting | Updated |
34 43 05.39
Formerly: 34 43 16.39 |
Airfield light support structures
Formerly: Airfield aluminum approach towers |
Updated, renamed and renumbered |
34 43 13.11
Formerly: 34 43 23.19 |
Airfield beacons and towers
Formerly: Aerodrome beacons |
Updated, renamed and renumbered |
34 43 13.13 | Airfield threshold runway identification lights | Updated |
34 43 13.14 | Airfield visual alignment guidance system | New |
34 43 13.15
Formerly: 34 43 10 |
Airfield illuminated guidance signs
Formerly: Airfield illuminated guidance signs |
Updated, renamed and renumbered |
34 43 13.16 | Airfield runway and taxiway inset lighting | Updated |
34 43 13.17
Formerly: 34 43 13.19 |
Airfield elevated edge lighting | Updated and renumbered |
34 43 13.18
Formerly: 34 43 13.23 |
Airfield runway guard lights | Updated and renumbered |
34 43 13.23
Formerly: 34 43 16.23 |
Airfield simplified short approach light system with runway alignment indicator lights (SSALR)
Formerly: Airfield short approach lighting system |
Updated and renumbered |
34 43 13.24 | Airfield simplified short approach light system-(SSALS) | New |
34 43 13.26
Formerly: 34 43 16.26 |
Airfield omni-directional approach lighting equipment
Formerly: Airfield omni-directional approach lighting system |
Updated, renamed and renumbered |
34 43 13.30 | Airfield medium intensity approach light system (MALS) | New |
34 43 13.31 | Airfield medium intensity approach light system with runway alignment indicator lights (MALSR) | New |
34 43 13.32 | Airfield medium intensity approach lighting system with sequenced flashing lights (MALSF) | New |
34 43 13.35 | Approach lighting system CAT.II or CAT.III - ALSF-2 | New |
34 43 13.36
Formerly: 34 43 16.36 |
Airfield precision-approach path indicator equipment
Formerly: Airfield precision approach path indicator (PAPI) |
Updated, renamed and renumbered |
34 43 13.43
Formerly: 34 43 23.43 |
Airfield apron floodlighting | Updated, renamed and renumbered |
34 43 23.16 | Airfield wind cones
Formerly: Wind direction indicators |
Updated and renamed |
34 43 26.16 | Airfield lighting PLC control equipment | Updated |
34 43 26.19
Formerly: 34 43 26.23 |
Airfield lighting regulator assembly | Updated and renumbered |
34 73 16.13 | Aircraft static grounding | Updated |
35 01 40.51
Formerly: 35 42 60 |
Waterway maintenance dredging
Formerly: Waterway channel maintenance |
Renamed and renumbered |
35 01 40.92
Formerly: 35 42 19 |
Preservation of water courses and wetlands | Updated and renumbered |
35 20 24
Formerly: 35 20 23 |
Dredging | Renumbered |
NMS summary of updates 2016-01
A series of corrections were made as part a of a general quality assurance review. Thousands of punctuation and spelling changes were made to improve consistency and ensure Canadian spelling throughout, for example 'colour' rather than 'color', 'fibre' rather than 'fiber'.
Enhancements were also made to align with SectionFormat™, such as listing standards under a heading of Reference standards. For consistency in tab levels, Abbreviations, Definitions and Reference standards were all promoted to top-level article Titles. Other changes were made to reflect specification writing language such as changing the requirement to submit (rather than provide) engineer sealed drawings.
There are over one hundred references to Codes Canada 2015 throughout. Each was reviewed and updated to the 2015 editions. There are a few exceptions related to seismic design that require additional review before updating code references are updated.
A few sections were renumbered or re-Titled to align with MasterFormat® and a more extensive adjustment will be released on the next NMS publication.
Technical updates
Section | Title | Status |
---|---|---|
01 23 00
Formerly: 01 23 10 |
Alternatives | Renumbered |
02 03 43
Formerly: 02 43 13.05 |
Period structure relocating
Formerly: Historic - Structure relocation |
Updated, renamed and renumbered |
08 36 19 | Multi-leaf vertical lift doors | Renamed and renumbered |
09 91 13 | Exterior painting | Updated |
09 91 13.23
Formerly: 09 97 19 |
Exterior painting of structural steel
Formerly: Painting exterior metal surfaces |
Updated, renamed and renumbered |
31 11 00 | Clearing and grubbing | Updated |
31 31 19.13 | Chemical vegetation control | Updated |
31 32 19.13 | Geogrid soil stabilization | Updated |
31 32 19.16
Formerly: 31 32 19.01 |
Geotextile soil stabilization
Formerly: Geotextiles |
Updated, renamed and renumbered |
32 01 90.33 | Tree and shrub preservation | Updated |
32 32 34 | Reinforced soil retaining walls | Updated |
32 33 00
Formerly: 32 37 00 |
Site furnishings
Formerly: Exterior site furnishings |
Updated, renamed and renumbered |
33 32 13.13
Formerly: 32 32 13.13 |
Packaged sewage lift, wet well type | Renumbered |
33 47 13
Formerly: 31 32 19.02 |
Pond and reservoir liners
Formerly: Geomembranes |
Updated, renamed and renumbered |
35 31 19 | Revetments | Updated |